Text of regulation 44
Foreign Exchange Rate Variation
44. Foreign Exchange Rate Variation .- (1) The generating company may hedge
foreign exchange exposure in respect of the interest on foreign currency loan and
repayment of foreign loan acquired for the generating station in part or full in the
discretion of the generating company.
(2) Every generating company shall recover the cost of hedging of foreign
exchange rate variation corresponding to the normative foreign debt, in the relevant year
on year-to-year basis as expense in the period in which it arises and extra rupee liability
corresponding to such foreign exchange rate variation shall not be allowed against the
hedged foreign debt.
(3) To the extent the generating company is not able to hedge the foreign exchange
exposure, the extra rupee liability towards interest payment and loan repayment
corresponding to the normative foreign currency loan in the relevant year shall be
permissible provided it is not attributable to the generating company or its suppliers or
contractors.
(4) Every generating company shall recover the cost of hedging and foreign
exchange rate variation on year-to-year basis as income or expense in the period in which
it arises.
Previous and next
Questions people ask
Is regulation 44 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 is recorded.