Regulation 29, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011: Late Payment Surcharge
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 - Regulation 29
Text of regulation 29
Late Payment Surcharge
29. Late Payment Surcharge .- In case the payment of any bill for charges payable
under these regulations is delayed by a beneficiary beyond a period of 60 days from the
date of billing a late payment surcharge at the rate of 1.25% per month shall be levied by
the generating company.
1 Subs. for “eighty paise” vide Not No. HPERC/F (5)(3)(1) (Gen.) dated 1
st
Nov., 2013 published in
the R H.P. dated 4
th
November, 2013 at p. 4606.
Compendium of HPERC Regulations, March 2021 25
Previous and next
Questions people ask
Is regulation 29 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 is recorded.