Text of regulation 29

Late Payment Surcharge

29. Late Payment Surcharge .- In case the payment of any bill for charges payable under these regulations is delayed by a beneficiary beyond a period of 60 days from the date of billing a late payment surcharge at the rate of 1.25% per month shall be levied by the generating company. 1 Subs. for “eighty paise” vide Not No. HPERC/F (5)(3)(1) (Gen.) dated 1 st Nov., 2013 published in the R H.P. dated 4 th November, 2013 at p. 4606. Compendium of HPERC Regulations, March 2021 25

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011

Questions people ask

Is regulation 29 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 is recorded.