Regulation 5, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011: Multi Year Tariff (MYT) Framework

The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 - Regulation 5

Text of regulation 5

Multi Year Tariff (MYT) Framework

5. Multi Year Tariff (MYT) Framework.-(1) The Commission shall adopt multiyear tariff framework for determination of tariff for each year of the control period. (2) The multiyear tariff framework shall be based on the following: - (a) Business plan (with plant-wise details) for the entire control period, which the applicant shall submit to the Commission for approval, prior to the beginning of the control period; (b) Forecast of expected tariff for sale of power which shall be submitted by the generating company (plant-wise) for each year of the control period, 1 Sub. vide Not. No. HPERC-F(1)-2/2018 dated 22 nd November, 2018 published in the R.H.P. 27 th November, 2018 at p. 6249-6255. 8 Compendium of HPERC Regulations, March 2021 based on reasonable assumptions of the underlying financial and operational parameters, as submitted in the business plan; (c) Trajectory for specific parameters, stipulated by the Commission, where the performance of the applicant is sought to be improved through incentives and disincentives;

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011

Questions people ask

Is regulation 5 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011 is recorded.