Regulation 9, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011: Capital Investment
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011 - Regulation 9
Text of regulation 9
Capital Investment
9. Capital Investment.- (1) The Commission shall approve capital investment plan
of the licensees for the control period commensurate with load growth, rural electrification,
system extension, distribution loss reduction and quality improvement proposed in the
business plan.
(2) The distribution licensee shall be required to take scheme wise approval for
capital investment for creation of new assets at 33 kV and above, but for creation of new
assets below 33 kV and network augmentation approval will be required as block of
scheme.
(3) Capital investment plan submitted by the licensee shall also provide details of
ongoing projects that will spill into the control period and new projects for creation of new
assets at 33 kV and above that will commence during the control period but may extend
beyond the control period.
(4) The investment plan shall be scheme-wise and with respect to each
circle/scheme shall include-
(a) purpose of investment (i.e. replacement of existing assets, meeting load
growth, technical loss reduction, non-technical loss reduction, meeting
reactive energy requirements, customer service improvement, improvement
in quality and reliability of supply, etc) ;
(b) Capital Structure;
(c) Capitalisation Schedule;
1
[(d) Financing plan showing the details for funding of the proposed investment
i.e. through loan from financial institutions, equity grants and subsidies and
consumer contribution, if any, for the specific work and utilization of other
capital receipts as per provisions of HPERC (Recovery of Expenditure for
Supply of Electricity) Regulations, 2012;]
(e) Cost-benefit analysis; and
(f) Improvement in operational efficiency envisaged in the control period, etc.
(5) For the Annual Performance Review, the distribution licensee shall submit the
actual capital expenditure incurred and capitalisation during the year under review along
with the Annual Performance Review Filing.
1 Subs. vide Not. No. HPERC/F(5)(3)(1)(Retail) dated 1
st
November, 2013 published in the R.H.P.
dated 4
th
November, 2013 at p. 4579 – 4596 and before its substitution Clause (d) as under:
“(d) Financing Plan; ’’
10 Compendium of HPERC Regulations, March 2021
1
[(6) The Commission may review the capital expenditure incurred and
capitalization at the end of each year of the control period vis-à-vis the approved capital
expenditure and capitalization schedule. In the normal course, the Commission shall not
revisit the approved capital investment plan (capital expenditure and the capitalization
schedule) on yearly basis during the control period and adjustments to depreciation,
interest on capital loan and return on equity on account of variations for the actual capital
expenditure incurred and capitalization made vis-à-vis approved capital investment plan
(capital expenditure and capitalization), shall be done during the mid-term performance
review and at the time of end of control period true up.]
(7) In case the capital expenditure is required for emergency work which has not
been approved in the Capital Investment Plan, the licensee shall submit an application,
containing all relevant information along with reasons justifying emergency nature of the
proposed work, seeking approval by the Commission. The licensee shall take up the work
prior to the approval of the Commission provided that the emergency nature of the scheme
has been certified by its Board of Directors.
2[(8) The licensee shall submit a report for every quarter detailing the progress of
the capital expenditure and capitalisation undertaken against that proposed in the Capital
Investment Plan, on or before the last Day of the month succeeding the respective quarter
for review by the Commission.]
Previous and next
Questions people ask
Is regulation 9 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011 is recorded.