Regulation 4, The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011: Multi Year Tariff (MYT) Framework
The Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011 - Regulation 4
Text of regulation 4
Multi Year Tariff (MYT) Framework
4. Multi Year Tariff (MYT) Framework.- The Commission shall adopt multiyear
tariff framework for approval of ARR and expected revenue from tariffs and charges for
the control period. The multiyear tariff framework shall be based on the following: -
(a) Business plan of the distribution licensee for the entire control period to be
submitted to the Commission for approval, prior to the beginning of the
control period;
(b) Applicant’s forecast of expected wheeling tariff and retail supply tariff
for each year of the control period, based on reasonable assumptions of the
underlying financial and operational parameters, as submitted in the
business plan;
(c) Trajectory for specific parameters shall be stipulated by the
Commission, where the performance of the applicant is sought to be
improved through incentives and disincentives;
1
[(cc) “Uncontrollable parameters” for a distribution licensee shall inter-
aliacomprise of the following factors, which were beyond the reasonable control
of the licensee, and could not be mitigated by the licensee:—
(a) Force Majeure events,
(b) Change in Law, judicial pronouncements and Orders of the Central Government,
State Government or Commission,
(c) Variation in the number or mix of Consumers or quantities of electricity
supplied to Consumers,
(d) Variation in the cost of power purchase due to variation in the rate of power
purchase from approved sources, subject to clauses in the power purchase
agreement or arrangement approved by the Commission,
(e) Variation in fuel cost,
(f) Change in power purchase mix,
(g) Inflation,
(h) Transmission Charges,
(i) Variation in market interest rates for long-term loans,
(j) Taxes and Statutory levies,
(k) Taxes on income,
(l) Income from the realisation of bad debts written off:
Provided that where the applicant believes, for any variable not specified
above, that there is a material variation or expected variation in performance for any
Financial Year on account of uncontrollable factors, such applicant may apply to the
Commission for inclusion of such variable and the Commission may incorporate the
same, under this regulation for such Financial Year:]
2
[(d) annual performance review (APR) shall be conducted for the variations in
performance on account of uncontrollable parameters for each year of the control
1
Subs. vide Not. HPERC-F(1)-1/2018 dated 22nd November, 2018 published in R.H.P. dated 27th November, 2018
at p. 6265-6277.Before its substitution it stood as under:-
“Uncontrollable parameters shall include power purchase and power sale by the distribution
licensee;”
2
Cls. (d) and (dd) subs. for Clause (d) vide Not. No. HPERC/F(5)(3)(1)(Retail) dated 1
st
November,
2013 published in the R.H.P. dated 4
th
November, 2013 at p. 4579 – 4596 and before its substitution Cls.(d)
read as under:-
Compendium of HPERC Regulations, March 2021 7
period vis-à-vis the ARR approved in the first year of the control period for those
years;
(dd) mid-term performance review (MPR) shall be conducted for the year after the
mid-year of the control period and shall comprise the annual performance review
for that year on account of uncontrollable parameters and for the variations in
performance on account of controllable parameters for the control period vis-à-
vis the ARR approved in the first year of the control period;]
(e) Profit sharing shall be applied on the profits arising from the distribution
licensee’s better performance vis-à-vis distribution loss targets and targets for the
other controllable parameters specified by the Commission. The distribution
licensee shall be free to utilise its share in the profit.
1
[(f) Variation in revenue/cost on account of uncontrollable parameters shall be trued
up annually during the annual performance review.]
Previous and next
Questions people ask
Is regulation 4 of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011 is recorded.