Regulation 40, The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010: Repeal and savings
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 - Regulation 40
Text of regulation 40
Repeal and savings
40. Repeal and savings.- (1) Save as otherwise provided in these regulations, the
Himachal Pradesh Electricity Regulatory Commission (f for Open Access) Regulations,
2005 and regulation 7 of the Himachal Pradesh Electricity Regulatory Commission (Cross
Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006
are hereby repealed.
(2) Notwithstanding such repeal anything done or any action taken or purported
to have been done or taken under the repealed regulations shall, in so far it is not
inconsistent with the provisions of these regulations, be deemed to have been done or taken
under the corresponding provisions of these regulations.
By order of the Commission
-Sd-
Secretary
22 Compendium of HPERC Regulations, March 2021
Notifications and orders issued
Under
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity,
Long-term and Medium-term intra-State Open Access and Related Matters)
Regulations, 2010
1
[Commencement of regulations, 3, 5 to 25 and 27 to 40 of the Himachal Pradesh Electricity
Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Open Access
and Related Matters) Regulations, 2010]
NOTIFICATION
Dated: 2
nd
August, 2011
No. HPERC(TA)/418.- Whereas the Himachal Pradesh Electricity Regulatory Commission
has approved the detailed procedure on dated 9
th
December, 2010, prepared and submitted
by the Nodal Agency i.e. the State Transmission Utility, the Nodal Agency for the grant of
connectivity, long-term open access and medium-term open access to the intra-State
transmission system, under regulation 26 of the Himachal Pradesh Electricity Regulatory
Commission (Grant of Connectivity, Long-term and Medium-term Open Access and Related
Matters) Regulations, 2010 and has been issued and hosted by the Nodal Agency on its
website: www.hpptcl.gov.in
Now, therefore, in exercise of the powers conferred by sub-regulation (2) of
regulation 1 of the Himachal Pradesh Electricity Regulatory Commission (Grant of
Connectivity, Long-term and Medium-term Open Access and Related Matters) Regulations,
2010, the Himachal Pradesh Electricity Regulatory Commission hereby notifies in relation
to the grant of connectivity, long term open access and medium term open access to the
Intra-State Transmission System, the 5
th
day of the September, 2011 the date on which the
provisions of regulations 3, 5 to 25 and 27 to 40 of the said regulations shall come into force.
By order of the Commission
-Sd-
Secretary
1
Published in R H.P. dated 3
rd
September, 2011 at p. 2685-2686.
Compendium of HPERC Regulations, March 2021 23
1
[The Himachal Pradesh Electricity Regulatory Commission (Determination of Open
Access Charges) Order, 2010]
Text of this Order is printed under the Himachal Pradesh Electricity Regulatory Commission (Cross
Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006.
2
[The Himachal Pradesh Electricity Regulatory Commission (Determination of Open
Access Charges) Order, 2011]
ORDER
Dated: 1
st
December, 2011
No. HPERC/418.- In exercise of powers conferred under regulations 16,17,26, 27 and 42 of
the Himachal Pradesh Electricity Regulatory Commission (Short term Open Access)
Regulations, 2010 and regulations 27, 28 and 39 of the Himachal Pradesh Electricity
Regulatory Commission (Grant of Connectivity, Long-term and Medium-term intra-State
Open Access and Related Matters) Regulations, 2010, regulation 33 and 48 of Himachal
Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of
Transmission Tariff) Regulations, 2011 and regulation 3 and 10 of Himachal Pradesh
Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and
Phasing of Cross Subsidy) Regulations, 2006, the Himachal Pradesh Electricity Regulatory
Commission makes the following order namely:-
1. Short title and Commencement.- (1) This Order may be called Himachal Pradesh
Electricity Regulatory Commission (Determination of Open Access Charges) Order, 2011.
(2) This Order shall come into force on the date of its publication in the Rajpatra,
Himachal Pradesh.
2. Applicability.- This Order shall remain in force upto 31
st
March, 2012 unless
allowed to be continued for further period with such variations or modifications as may be
ordered by the Commission.
3. Determination of Open Access Charges:- The Commission hereby determines the
Transmission Charges, Wheeling charges, SLDC charges and Cross Subsidy Surcharge
payable by Open Access Customers for the usage of existing Transmission system of
Himachal Pradesh State Transmission Corporation Ltd (HPPTCL) HPSEB Ltd and the
Services of SLDC of the State as under:-
(A) Transmission Charges
In view of the designation of HPPTCL as State Transmission Utility and transfer of
certain existing works of the erstwhile HPSEB by H.P. Government to HPPTCL vide
its order dated 10.6.2010, the Commission approved a separate ARR of Rs. 11.71
crore for2011-12 in respect of the State transmission system vide its order dated
14.7.2011. Based on this ARR, the transmission charges payable by the Open Access
consumers for the usage of the existing Transmission System of HPPTCL are
determined out as under:-
(i) For Short term Open Access Consumers
ARR of HPPTCL for FY 2011-12 as per clause 5-30
of MYT Order for HPPTCL dated 14.7.2011 Rs. 11.71 Cr.
Total estimated requirement of annual energy
1
Published in R H.P. dated 25
th
August, 2010 at p. 4048-4049.
2
Published in R H.P. dated 09.12.2011 at p. 4439-4442.
24 Compendium of HPERC Regulations, March 2021
power at State Periphery (i.e. excluding HPSEBL’s
own generation and purchase from projects
directly connected to Distribution System) = 5514.33 MU
Transmission charges 11.71x10x100 = 2.12 paise/kwh
for short term open access 5514.33
(i) For Long and Medium term Open Access Consumers.
In absence of firm agreement between HPPTCL and HPSEBL about the
quantum of contracted capacity, the Commission has considered the same as
900 MW by taking account the estimated average demand of the State and the
estimated quantum energy required to be transferred on the transmission
system. Accordingly open access charges for the existing transmission system
of the HPPTCL are determined for long term and medium term open access
users as under :-
Transmission charges = 11.71x 10000000 Rs. 10843/MW/Month
900 x 12
Note:- 1. Transmission charges for (i) as well as (ii) shall be levied on the
energy/power injected into the State Transmission System.
2. In case of variation of contracted capacity, the recovery from
distribution licensee, through transmission charges, shall be
limited to the approved ARR.
(B) Wheeling Charges
Consequent to transfer of the State Transmission System to HPPTCL as per H.P.
Government’s order dated 10.6.2010, the EHV system of HPSEBL now forms a
part of the distribution system. Since the per unit costs of wheeling at the EHT
and HT level shall be substantially lower than the average wheeling cost, the
Commission finds it prudent to fix the voltage wise wheeling charges. The
Commission has accordingly apportioned the wheeling cost of Rs. 783.23 crores
as determined in the Tariff Order dated 19.07.2011 to various voltage classes and
determined the wheeling charges for the EHT (66 kV and above), HT (11 kV and
above) and other voltage levels (upto 11 kV) of the distribution system. Certain
reasonable assumptions have however been made, wherever required, in view of
the non availability of complete data as also mentioned in the tariff order dated
19.7.2011. The charges determined by Commission are as under:-
S.
No.
Description EHT(≥
66kV)
HT( ≥ 11
kV)
Less than 11
kV
(i) Total cost Apportioned (Rs. in Crores) 268.27 288.13 226.82
(ii) Cost allocation brought forward from
the next higher voltage block) {(i-
v*vi)/1000} [(Rs. in Crores)]
0 204.74 217.10
(iii) Total cost Allocation (i+ii)(Rs. in
Crores)
268.27 492.87 443.92
(iv) Total energy quantum (Sales relevant to
determination of per unit rate) in MU
7090.19 5411.3 2383.57
(v) Energy sales 1678.89 3027.73 2383.57
(vi) Rate of wheeling charges in
Paise/Unit(iii/iv*1000 of previous
column)
38 91 186
Compendium of HPERC Regulations, March 2021 25
(i) Wheeling charges shall be levied on the energy drawn at the delivery point in
the distribution system.
(ii) In case the power is withdrawn from the distribution system at a normal
voltage level which is different from the voltage level for injection of power
into the distribution system, the wheeling charges corresponding to the lower
voltage level shall be applicable.
(C) SLDC/Operating charges:-
SLDC/Operating charges @ Rs. 2000/day or part of the day for each
transaction. These charges shall be levied only once for each open access
transaction even if the both state transmission and distribution systems are
involved.
(D) Cross Subsidy surcharge (Rs/Unit):-
The sub regulation 2 of regulation 3 stipulates that the cross subsidy surcharge
shall be determined by the Commission on a methodology and surcharge
formula specified in the National Tariff Policy, which is given as under:-
S = T – [C (1+L/100) +D]
Explanation .- For the purpose of this regulation. -
(a) “S” is the Surcharge
(b) “T” means Tariff payable by the relevant category of consumers
(c) “C” is the Weighted average cost of power purchase of top 5% at
the margin excluding liquid fuel based generation and renewable
power
(d) “D” is the Wheeling Charge
(e) “L” is the system losses for the applicable voltage level, expressed
as a percentage
Based on above the cross subsidy surcharge for various categories of is as
follows:-
Category For 21 hours of the
day (i.e. other than
peak load hours)
For Peak load
hours of the
day
a) Cross-Subsidy Surcharge for Large
Supply (LS) EHT Category
(Rs./Unit)
Nil
2.37
b) Cross subsidy Surcharge for LS HT
Category (Rs./Unit)
Nil 2.11
c) Cross Subsidy Surcharge for Bulk
Supply (BS) HT Category
Nil Nil
d) Cross subsidy Surcharge for Water
and Irrigation Pumping Supply
(WIPS) HT category (Rs./Unit)
0.11 2.36
The Cross Subsidy Surcharge shall be levied separately for peak load
hours and remaining hours of the day for the quantum of power and Nos. of
hours falling in each of these two categories of time blocks for which Open
26 Compendium of HPERC Regulations, March 2021
Access is allowed. The Cross Subsidy Surcharge shall be levied on the
energy withdrawn at the delivery point in the distribution system through
open access.
(E) In addition to above charges, the transmission as well as distribution losses
shall be absorbed by the Open Access consumers in kind as per provisions of
the Open Access regulations and shall be credited to the respective licensees
through energy accounting mechanism to the respective licensees.
(F) Additional Surcharge:
This shall be determined by the Commission in accordance with the Sub-
regulation 3 of regulation 6 of HPERC (Cross Subsidy Surcharge, Additional
Surcharge and Phasing of Cross Subsidy) Regulations, 2006 if the
distribution licensee registers and substantiates any claim in this regard.
By Order of the Commission
-Sd-
Secretary
Previous and next
Questions people ask
Is regulation 40 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.