Regulation 30, The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010: Payment of transmission/wheeling charges and fees and Charges for the State Load Despatch Centre
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 - Regulation 30
Text of regulation 30
Payment of transmission/wheeling charges and fees and Charges for the State Load Despatch Centre
30. Payment of transmission/wheeling charges and fees and Charges for the State
Load Despatch Centre.- (1) The transmission/wheeling charges in respect of the long-term
customer and medium-term customer shall be payable directly to the respective licensee:
Provided that the State Transmission Utility/licensee/nodal agency may be
designated by the Commission as the agency for the purpose of collecting and disbursing the
transmission/wheeling charges for intra-State transmission/ distribution system:
Provided further that when the State Transmission Utility/ licensee/nodal agency is
so designated as the agency as aforesaid, the transmission/wheeling charges shall be paid to
it:
Provided further that the State Transmission Utility/licensee/nodal agency so
designated, shall enter into agreements with the long-term customers and medium-term
customers for collection of transmission/wheeling charges and with the transmission/
distribution licensees whose intra-State transmission/ distribution system is being used, for
disbursement of transmission/wheeling charges as received, pro rata to the transmission
/wheeling charges payable to the licensees and to the State Transmission Utility:
Provided further that the State Transmission Utility/licensee/nodal agency, so
designated, shall be entitled to reimbursement of reasonable costs incurred by it in collecting
the transmission/wheeling charges of the other transmission/distribution licensees, as
approved by the Commission.
(2) The fees and charges for the State Load Despatch Centre shall be directly payable
by the long-term customer and medium-term to the State Load Despatch Centre.
Previous and next
Questions people ask
Is regulation 30 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.