Regulation 18, The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010: Application for medium-term open access
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 - Regulation 18
Text of regulation 18
Application for medium-term open access
18. Application for medium-term open access.- (1) The application for grant of
medium-term open access shall contain such details as may be laid down under the detailed
procedure and shall, in particular, include the point of injection into the grid, point of drawl
from the grid and the quantum of power for which medium-term open access has been
applied for.
(2) The start date of the medium-term open access shall not be earlier than 5 months
and not later than 1 year from the last day of the month in which application has been made.
Previous and next
Questions people ask
Is regulation 18 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.