Regulation 3, The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010: Scope
The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 - Regulation 3
Text of regulation 3
Scope
3. Scope. - These regulations, after they come into force, shall apply to the grant of
connectivity, long-term and medium-term open access in respect of intra-State transmission
system and/or distribution system of the licensees in the State including when such system is
used in conjunction with the inter-State transmission system:
Provided that a person seeking open access to the intra-State transmission system
and/or distribution system,
1
[unless already connected,] cannot apply for long-term access or
medium-term open access without applying for connectivity:
1
Ins. vide Not. No. HPERC/ 418 dated 7
th
December, 2012, published in the R.H.P. dated 10
th
December, 2012 at p. 5409-5415.
4 Compendium of HPERC Regulations, March 2021
Provided further that a person may apply for connectivity and long-term open
access or medium-term open access simultaneously.
1
[3- A. Eligibility for Open Access.- (1) Subject to the provisions of these regulations
and of sub-sections (2), (3) and (4) of section 42 of the Act, the open access to the
distribution system of the distribution licensee is permitted to all the consumers who
either -
(i) require a supply of electricity, for their own use, with the contract demand
exceeding one MVA; or
(ii) have installed captive generating plants and require open access to the
distribution system for conveyance of power to the destination of use at the
consumer premises:
Provided that the Commission may, by order, permit open access in the
distribution system to other consumers, subject to such terms and conditions and at
such time, as it may consider feasible:
Provided further that the Commission may, after considering the operational
constraints and the merits of each case before it, permit open access to the
distribution system to such consumers, who have contract demand of 1 MVA or less
and require power for their own use from the renewable energy generating sources
located in Himachal Pradesh.
(2) Subject to sub-regulation (1) and other provisions of these regulations, the
licensees, generating companies, captive generating plants and such consumers who have
been permitted open access under sub-regulation (1) are eligible for open access to the intra-
State transmission system of the State Transmission Utility or of any transmission licensee
and the same shall accordingly be so granted on payment of transmission and other charges
as applicable.
(3) Subject to sub-regulation (1) and other provisions of these regulations, the
licensees, generating companies, captive generating plants and such consumers who have
been permitted open access under sub-regulation (1) are eligible for open access to the
distribution system of the distribution licensee and the same shall accordingly be so granted
on payment of wheeling and other charges as applicable.
(4) A person having been declared insolvent or bankrupt or having outstanding dues,
of more than two months’ billing, to the distribution/transmission licensee at the time of
application shall not be eligible for open access:
Provided that where the dispute regarding outstanding dues is pending before any
Forum or Court of law and the stay is granted, in that case the person shall be eligible for
seeking open access.]
Previous and next
Questions people ask
Is regulation 3 of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010 is recorded.