Power to remove difficulties
42. Power to remove difficulties.- If any difficulty arises in giving effect to any of the
provisions of these regulations, the Commission may, by general or special order, direct the
transmission licensee/(s), the distribution licensee/(s), the State Load Despatch Centre, the
generators, the nodal agency, the State Transmission Utility and the open access customer to
take such suitable action, not being inconsistent with the Act, as may appear to the
Commission to be necessary or expedient for the purpose of removing such difficulties.
Previous and next
Questions people ask
Is regulation 42 of the Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 is recorded.