Regulation 32, The Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010: Collection and disbursement of wheeling charges, and operating charges

The Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 - Regulation 32

Text of regulation 32

Collection and disbursement of wheeling charges, and operating charges

32. Collection and disbursement of wheeling charges, and operating charges.- (1) The wheeling charges and the operating charges payable by the persons allowed short-term open access in distribution system shall be collected and disbursed by the nodal agency. (2) The wheeling charges collected for use of the distribution system for each point of injection and each point of drawl shall be disbursed by the nodal agency in the following manner, namely- (a) the distribution licensee- 25%; (b) the long-term open access customers -75%; Provided that the wheeling charges shall be disbursed to the long-term customers in proportion to the monthly wheeling charges payable by them.

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010

Questions people ask

Is regulation 32 of the Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 is recorded.