Regulation 28, The Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010: Unscheduled Inter-change (UI) Charges
The Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 - Regulation 28
Text of regulation 28
Unscheduled Inter-change (UI) Charges
28. Unscheduled Inter-change (UI) Charges.- (1) All transactions for intra-State
entities under these regulations, shall be accounted for and included in the respective day-
ahead net interchange schedules of the concerned intra-State entity issued by the State Load
Despatch Centre.
(2) Based on net metering on the periphery of each intra-State entity, composite UI
accounts shall be issued for each intra-State entity on a weekly cycle.
(3) Any mismatch between the scheduled and the actual drawl at drawl points and
scheduled and the actual injection at injection points for the intra- State entities shall be
determined by the State Load Despatch Centre and covered in the intra-State Availability
Based Tariff (ABT).
10 Compendium of HPERC Regulations, March 2021
(4) The UI rate for intra-State entity shall be 105% (for over-drawls or under
generation) and 95% (for under-drawls or over generation) of UI inter-State rate.
Previous and next
Questions people ask
Is regulation 28 of the Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 is recorded.