Regulation 20, The Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010: Unscheduled Inter-change (UI) Charges
The Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 - Regulation 20
Text of regulation 20
Unscheduled Inter-change (UI) Charges
20. Unscheduled Inter-change (UI) Charges.- (1) All transactions for intra-State
entities by the nodal agency under these regulations, shall be accounted for and included in
the respective day-ahead net interchange schedules of the intra-State entity issued by the
State Load Despatch Centre.
(2) Based on net metering on the periphery of each intra-State entity, composite UI
accounts shall be issued for each intra-State entity on a weekly cycle.
(3) Any mismatch between the scheduled and the actual drawl at drawl points and
scheduled and the actual injection at injection points for the intra- State entities shall be
determined by the State Load Despatch Centre and covered in the intra-State Availability
Based Tariff (ABT).
(4) The UI rate for intra-State entity shall be 105% (for over-drawls or under
generation) and 95% (for under-drawls or over generation) of inter-State UI rate.
8 Compendium of HPERC Regulations, March 2021
Previous and next
Questions people ask
Is regulation 20 of the Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 is recorded.