13. Curtailment in case of transmission operational constraints.-(1) The State Load
Despatch Centre may curtail power flow on any transmission corridor, by cancelling or re-
scheduling any transaction, if in its opinion cancellation or curtailment of any such
transaction is likely to relieve the transmission operational constraint or improve grid
security.
(2) In case of curtailment of the approved schedule by the State Load Despatch
Centre, transmission charges shall be payable pro-rata in accordance with the curtailed
schedule:
Provided that operating charges shall not be revised in case of curtailment under sub-
regulation (1).
Explanation.– For the purpose of this regulation, the expression “operational constraints”
shall include the availability of the adequate capacity in the transmission system, appropriate
metering and energy accounting system where the electricity to be transmitted can be
correctly measured and accounted for and such other factors which may have an impact on
the transmission licensee’s business of supplying electricity to consumers in the area of
supply.
Previous and next
Questions people ask
Is regulation 13 of the Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Short Term Open Access) Regulations, 2010 is recorded.