Regulation 14, The Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010: Interpretation
The Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 - Regulation 14
Text of regulation 14
Interpretation
14. Interpretation.– All issues arising in relation to interpretation of these regulations
shall be determined by the Commission and the decision of the Commission on such issues
shall be final.
By Order of the Commission
-Sd-
Secretary
Compendium of HPERC Regulations, March 2021 11
1
[Annexure-I *********]
2
[SCHEDULE
[See sub-regulation (2A) of regulation 4]
Minimum Percentage for Renewable Power Purchase obligation
Year in which the original capacity of
the captive generating plant is
commissioned or augmented
Minimum Quantum of Purchase of percentage (%)
from renewable sources (in terms of energy in kWh)
of total consumption
Non-Solar Solar Total
2015-16 or before 11.00% 0.25% 11.25%
2016-2017 9.50% 2.50% 12.00%
2017-2018 9.50% 4.75% 14.25%
2018-2019 10.25% 6.75% 17.00%
2019-2020 10.25% 7.25% 17.50%
2020-2021 10.25% 8.75% 19.00%
2021-2022 10.50% 10.50% 21.00%
(a) The RPPO will be on total consumption of electricity by an obligated entity,
excluding consumption met from hydro-electric sources of power.
(b) In case the achievement of Solar RPPO compliance to the extent of 85% and above,
the remaining shortfall if any, can be met by excess Non-Solar energy purchased
beyond specified Non-Solar RPPO for that particular year.
(c) Further, in case on achievement of Non-Solar RPPO compliance to the extent of
85% and above, the remaining shortfall if any, can be met by excess solar energy
purchased beyond specified Solar RPPO for that particular year.
(d) In case where the capacity of CPP is augmented after 31-03-2016, the year in which
the capacity augmentation takes place shall be considered for applicability of RPPO
rates for the entire augmented capacity. Similarly, if the capacity is further
augmented, the year in which the latest augmentation takes place, shall be
considered for RPPO.]
1
Omitted Annexure-I vide Not. No. HPERC/438 dated 24
th
March, 2017, published in R.H.P. dated
27
th
March, 2017 at p. 8567-8570 which stood as under:-
Annexure-I
(SEE REGULATION 4(1))
Estimated RPPO (in MUs) from renewable sources
Financial year Years Total Energy Requirement in
Mus including T&D Losses
Minimum Solar Power
purchase Obligation in
Mus
Total Renewable Power
purchase Obligation in Mus
FY 12 2011-12 8244.00 0.82 825.22
FY 13 2012-13 8748.00 21.87 896.67
FY 14 2013-14 9168.00 22.92 939.72
FY 15 2014-15 9159.20 22.89 938.81
FY 16 2015-16 9719.37 24.30 1093.42
FY 17 2016-17 10312.40 25.78 1263.26
FY 18 2017-18 10926.18 54.63 1475.03
FY 19 2018-19 11575.04 86.81 1707.31
FY 20 2019-20 12260.97 122.60 1961.75
FY 21 2020-21 12986.08 259.72 2272.56
FY 22 2021-22 13752.57 412.57 2612.98
2
Ins. Schedule vide Not No. HPERC/438 dated 5
th
February, 2020 published in R.H.P. dated 7
th
February, 2020 at p. 10243-10245.
12 Compendium of HPERC Regulations, March 2021
Notifications and Orders issued
under
The HPERC (Renewable Power Purchase Obligation its Compliance) Regulations, 2010
1
[Designating “Directorate of Energy” as State Agency under RPPO Regulations, 2010]
NOTIFICATION
Dated: 19
th
June 2010
No.- HPERC/438: In exercise of the powers conferred by sub-regulation (1) of Regulation
6, read with clause (h) of regulation 2 of the Himachal Pradesh Electricity Regulatory
Commission (Renewable Power Purchase Obligation and its Compliance) Regulations,
2010, the Himachal Pradesh Electricity Regulatory Commission hereby designates the
“Directorate of Energy” which is an authority created under the administrative control of the
Government of Himachal Pradesh to promote power generation, as the State Agency for the
purposes of the said regulations.
By Order of the Commission
-Sd-
Secretary
2
[Applicability of Quantum of RPPO to Captive and Open Access Users/Consumers]
NOTIFICATION
Dated: 30
th
September, 2010
No. HPERC(TA)/438:- In exercise of the powers conferred by sub-regulation (1) of
Regulation 8, of the Himachal Pradesh Electricity Regulatory Commission (Renewable
Power Purchase Obligation and its Compliance) regulations, 2010, the Himachal Pradesh
Electricity Regulatory Commission hereby appoints the 1
st
day of November, 2010, as the
date on which the quantum of RPPO inclusive of transmission distribution losses mentioned
in sub regulation (1) of regulation 4 of regulations (ibid) shall become applicable to Captive
and Open Access User(s)/ Consumer(s).
By Order of the Commission
-Sd-
Secretary
1
Published in R. H.P. dated 24
th
June, 2010 at p. 1767-1768.
2
Published in R H.P. dated 5
th
Oct., 2010 at p. 5247.
Compendium of HPERC Regulations, March 2021 13
1
[The HPERC (Fixation of Fees and Charges for Accreditation of Renewable Energy
Generation Project) Order, 2010]
ORDER
Dated: 23
rd
October, 2010
No.-HPERC/438(TA): In exercise of the powers conferred by sub-regulation (4) of
regulation 6 of the Himachal Pradesh Electricity Regulatory Commission (Renewable Power
Purchase Obligation and its Compliance) Regulations, 2010, the Himachal Pradesh
Electricity Regulatory Commission hereby makes following order to fix the Fee and Charges
payable to the State Agency for Accreditation of Renewable Energy Generation Projects.
1. Short title.- This Order may be called Himachal Pradesh Electricity Regulatory
Commission (Fixation of Fees and Charges for Accreditation of Renewable Energy
Generation Project) Order, 2010.
2. Fees and Charges.-(1) One time Application Processing Fees: Rs.5,000/- per
application non-refundable shall be payable at the time of submitting application for
accreditation to the State Agency.
(2) One time Accreditation Charges: Rs.30,000/- per application shall be payable to
the State Agency upon grant of accreditation.
(3) Annual Charges for Accreditation: Rs.10,000/- per application shall be payable
by April 10, of each year.
(4) Accreditation Charges for Revalidation/extension of validity: Rs.15,000/- per
application shall be payable at the time of revalidation/ extension of validity of existing
accreditation at the end of five years, or any such period as may be determined by the
Commission from time to time, from the date of initial Accreditation unless otherwise
revoked prior to such validity period.
(5) The taxes and duties on fee and charges shall be applicable as per prevailing
norms.
3. Review of Fees and Charges.- The Control Period or Review Period of the fee and
charges shall be of three years unless allowed to be continued for further period with such
variations or modifications as may be ordered by the Commission of which the first year
shall be the period from the date of publication of this Order to March 31, 2011.
. By Order of the Commission
-Sd-
Secretary
1
Published in R H.P. dated 27
th
Oct., 2010 at p. 5667-5668.
14 Compendium of HPERC Regulations, March 2021
1
[ The HP Electricity Regulatory Commission (Fixation of Fees and Charges for Accreditation
of Renewable Generation Project and Distribution Licensee) Order, 2016]
ORDER
Dated: 08th March, 2016
No. HPERC/438 (TA).—In exercise of the powers conferred by sub-regulation (4) of
regulation 6 of the Himachal Pradesh Electricity Regulatory Commission (Renewable Power
Purchase Obligation and its Compliance) Regulations, 2010 and in supersession to this
office Order dated 14th August, 2015 i.e. HPERC (Fixation of Fees and Charges for
Accreditation of Renewable Energy Generation Project) Order, 2015 and after previous
publication, the Himachal Pradesh Electricity Regulatory Commission hereby makes
following Order, to fix the Fees and Charges payable to the State Agency, for Accreditation
of Renewable Energy Generation Projects and Distribution Licensee:—
1. Short title.—This Order may be called Himachal Pradesh Electricity Regulatory
Commission (Fixation of Fees and Charges for Accreditation of Renewable Energy
Generation Project and Distribution Licensee) Order, 2016.
2. Fees and Charges.—The following fees and charges shall be payable to the State Agency
by the Renewable Energy Generators as well as Distribution Licensee:
(i) One time Application Processing Fees: Rs. 5,000/- per application, non refundable,
shall be payable at the time of submitting application for accreditation to the State
Agency.
(ii) One time Accreditation Charges: Rs. 30,000/- per application shall be payable to the
State Agency upon grant of accreditation.
(iii) Annual Charges for Accreditation: Rs.10,000/- per application shall be payable by
10
th
April of each year.
(iv) Accreditation Charges for Revalidation/extension of validity: Rs. 15,000/- per
applicationshall be payable at the time of revalidation/ extension of validity of
existing accreditation at the end of five years, or any such period as may be
determined by the Commission from time to time, from the date of initial
Accreditation unless otherwise revoked prior to such validity period.
(v) The taxes and duties on fees and charges shall be applicable as per prevailing norms.
By order of the Commission,
Sd/
Secretary.
1
Published in R H.P. dated 8
th
March, 2016 at p. 8495.
Compendium of HPERC Regulations, March 2021 15
1
[The HPERC (Adjustment of Surplus/Shortfall of Renewable Energy Certificates or
Renewable Energy with respect of Renewable Purchase Obligation of FY 2016-17 in FY 2017-
18) Order 2017]
Notification
Shimla, the 17
th
July, 2017
No. HPERC/438.—In exercise of the powers conferred under Regulations 9, 11, 12 and 13
of the Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase
Obligations and its Compliance) Regulations, 2010, and all other powers enabling it in this
behalf, after previous publications, hereby makes the following order namely:—
ORDER
1. Short title and commencement.—(1) This Order may be called the Himachal Pradesh
Electricity Regulatory Commission (Adjustment of Surplus/Shortfall of Renewable Energy
Certificates or Renewable Energy with respect to Renewable Purchase Obligation of FY
2016-17 in FY 2017-18) Order, 2017.
(2) This Order shall come into force from the date of its publication in the Rajpatra,
Himachal Pradesh.
2. Adjustment of surpluses or deficits.—Renewable Power Purchase Obligations (RPPO)
compliance for FY 2016-17. Notwithstanding anything in the procedures, practices,
directions relating to the monitoring the implementation and compliance of the RPPOs,
surpluses or deficits in the compliance of RPPOs for FY 2016-17, which could not be
adjusted or complied by the obligated entity, as the case may be, till 31st March, 2017, the
obligated entities may adjust or comply surpluses or deficits occurred consequent to the
revision of RPPO targets under the Himachal Pradesh State Electricity Regulatory
Commission (Renewable Power Purchase Obligation and its Compliance)(Third
Amendment) Regulations, 2017, in the financial year 2017-18.
Place: Shimla. By Order of the Commission
Date: 17 .07.2017. Sd/-
(CHAMANDILTA)
Secretary
1
Published in R H.P. dated 18
th
July, 2017, 2010 at p. 4000.
Previous and next
Questions people ask
Is regulation 14 of the Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 is recorded.