18. Repeal and savings.- (1) Save as otherwise provided in sub-regulation (2) of
regulation 4 and in other provisions of these regulations, the Himachal Pradesh Electricity
Regulatory Commission (Licensees' Standards of Performance) Regulations, 2005 are
hereby repealed.
(2) Anything done or any action taken or purported to have been done or taken,
including any order, direction made or notice issued under the repealed regulations, prior
to the commencement of these regulations shall, in so far as it is not inconsistent with the
provisions of these regulations, be deemed to have been done or taken or issued under the
corresponding provisions of these regulations.
(3) As far as the licensee is concerned, notwithstanding anything to the contrary
contained in the HPERC (Guidelines for Establishment of Forum for Redressal of
Grievances of the Consumer) Regulations, 2003 framed by the Commission under section
181 of the Electricity Act, 2003, these regulations shall have overriding effect.
(4) Nothing in these regulations shall effect the rights and privileges of the
consumers under any other law including the Consumer Protection Act, 1986 (68 of 1986).
By Order of the Commission
-Sd-
Secretary
Compendium of HPERC Regulations, March 2021 11
SCHEDULE
(see regulation 2 (15), 4,5 and 17)
Guaranteed Standards of Performance Overall
Standards of
performance
Sl.
No.
Nature of service Maximum
Time Limit for
rendering
service
Minimum Compensation Leviable Target levels
Compensation
payable to
individual
consumer if the
event affects a
single consumer
Compensation
payable to individual
consumer if the event
affects more than one
consumer
(1) (2) (3) (4) (5) (6)
(1) Call Centre
(a) First response
against a Consumer
Call
3 Minutes Rs. 10/ in each
case of default
Not applicable Not applicable
(b) Registration of
Consumer Call and
issue of Docket
Number
5 Minutes Rs. 10/ in each
case of default
Not applicable Not applicable
(2) Consumer Related Services
A Fuse-off /Fault Calls:
(i) In urban areas 6 working hours Rs. 10/- for each
hour of delay
beyond
maximum
specified time
limit
Rs. 5/- for each
hour of delay
beyond maximum
specified time limit
99% of Fuse/
Fault complaints
received
(ii)
In rural areas
12 working
hours
(iii) In remote areas 24 working
hours
B Overhead Line and Cable /Under –ground Cable breakdowns:
(I)
(i)
Overhead Line and
Cable –
Overhead Line /
Cable breakdown in
urban areas
(a) Where
replacement of
pole is not
required:
24 working hrs.
Rs. 10/- for
each day of
default beyond
the maximum
specified time
limit
Rs. 5/- for each day
of default beyond
maximum specified
time limit
95% of line
breakdown
complaints
received
(b) Where
replacement of
pole is required:
36 working hrs
Rs. 10/- for
each day of
default beyond
maximum
specified time
limit
Rs. 5/- for each day
of default beyond
maximum specified
time limit
95% of the line
breakdown
complaints
received
(ii) Overhead Line /
Cable breakdown in
rural areas and
remote areas
(a) Where
replacement of
pole is not
required: 24
working hrs. for
rural and with-in
48 working hrs.
for remote areas
Rs. 10/- for
each day of
default beyond
maximum
specified time
limit
Rs. 5/- for each day
of default beyond
maximum specified
time limit
90% of Line
breakdown
complaints
received
12 Compendium of HPERC Regulations, March 2020
(b) Where
replacement of
pole is required:
72 working Hrs.
for rural and 144
working hrs. for
remote areas.
Rs. 10/- for
each day of
default beyond
maximum
specified time
limit
Rs. 5/- for each day
of default beyond
maximum specified
time limit
85% of Line
Breakdown
complaints
received
(II)
(i)
(ii)
(iii)
Under-ground
Cable break down-
in urban areas
in rural areas
in remote areas
48 working hrs.
70 working hrs
90 working hrs
Rs. 20/- for
each day of
default beyond
maximum
specified time
limit
Rs. 10/- for each
day of default
beyond maximum
specified time
limit
90% of the cable
breakdown
complaints
received
C Replacement of failed Distribution Transformer:
(i) in urban areas 8 working hrs. Rs. 20/- for each
day of default
beyond maximum
specified time
limit
Rs.10/- for each
day of default
beyond maximum
specified time
limit
95% of number
of transformers
reported failure.
(ii) in rural areas 32 working hrs.
(iii) in remote areas 56 working hrs.
D Replacement of damaged service line/wire:
(i)
In urban areas-
LT
HT
8 working hrs.
16 working hrs.
Rs. 10/- for each
day of default
beyond
maximum
specified time
limit
Rs.5/- for each day
of default beyond
maximum
specified time limit
95% of damaged
service line
complaints
received (ii) In rural and remote
areas -
LT
HT
16 working hrs.
32 working hrs.
E Complaints about meters
testing and checking for correctness of Meters
(i) In urban area 56 working hrs.
from registration
of complaint
Rs. 50/- each day
of default beyond
maximum
specified time
limit
Not applicable 90% of requests/
complaints
(ii)
In rural areas
120 working hrs.
from registration
of complaint
(iii) In Remote areas
160 working hrs
from registration
of complaint
F Consumers Defective/Stopped/Burnt Meter/Metering Equipment Replacement (*)-
(I) LT Consumers
(a) urban areas
(1) Replacement not
attributable to consumer’s
fault
56 working hrs from
the date of
registration of the
complaint
Rs. 100/- for each day
of default beyond
maximum specified
time limit
Not
applicable
Min. 90%
(2)
Replacement attributable
to consumer’s fault such as
tampering, defect in
consumer’s installation,
meter getting wet,
connecting unauthorized
additional load etc. and the
cost of the meter is
recoverable from the
consumer and meter is to
be supplied by the licensee
Rs. 100/- for each day
of default beyond
maximum specified
time limit
Not
applicable
Min. 90%
Compendium of HPERC Regulations, March 2021 13
–
(i) serving a notice to the
consumer for recovery of
cost of the meter
(ii) replacement of meter
(iii) replacement of meter
if consumer is providing
the meter.
56 working hrs from
the date of
registration of
complaint.
56 working hrs
after receiving the
payment from the
consumer
56 working hrs from
the receipt of the
meter from the
consumer and after
the corrective action,
if any, is taken by the
consumer.
(b) rural and remote Areas
(1) Replacement not attributable
to consumer’s fault
120 working hrs. from the
date of receiving
information / registration
of the complaint.
Rs. 100/- for
each day of
default beyond
maximum
specified time
limit.
Not
applicable
Min.
90%
(2) Replacement attributable to
consumer’s fault such as
tampering, defect in
consumer’s installation, meter
getting wet, connecting
unauthorized additional load
etc. and the cost of the meter
is recoverable from the
consumer and meter is to be
supplied by the licensee.
i) serving a notice to the
consumer for recovery of cost
of the meter
(ii) replacement of meter.
(iii) replacement of meter, if
consumer is providing the
meter.
56 working hrs from the
date of receiving
information/ registration
of complaint.
120 working hrs after
receiving the payment
from the consumer and
after the necessary and
corrective action, if any, is
taken by the consumer.
120 working hrs from the
receipt of meter from the
consumer and after the
necessary corrective
action, if any, is taken by
the consumer.
Rs. 100/- for
each day of
default beyond
maximum
specified time
limit.
Not
applicable
Min.
90%
(II) H.T. Consumers (for Urban, Rural and Remote Areas)
(1) Replacement not 7 days after receipt of Rs. 400/- for each Not Min.
14 Compendium of HPERC Regulations, March 2020
attributable to consumer complaint, provided meter
is available with the
licensee, otherwise within
1 month.
day of default
beyond specified
maximum time
limit
applicable 95%
(2) Replacement attributable to
consumer fault such as
tampering, defect in
consumer’s installation,
meter getting wet,
connecting unauthorized
additional load etc.
Rs. 400/- for each
day of default
beyond maximum
specified time
limit
Not
applicable
Min.
95%
and the cost of the meter is
recoverable from the
consumer and meter is to be
supplied by the licensee.
(i) serving a notice to the
consumer for recovery of
cost of the meter
(ii) replacement of meter.
(iii) replacement of meter if
consumer is providing the
meter.
7 days from the date of
receipt of complaint/
information.
7 days after receiving the
payment from the
consumer provided meter
is available with licensee,
otherwise within 1 month
7 days from the
registration of complaint
Note;-
(1) In case of supply being affected due to burnt meters then replacement has to be to be undertaken
within 1 day.
(2) Replacement of old electromechanical meters may be done by electronic meters. If the consumer is
providing the meter then he must be advised to provide electronic meter.
(3) If a consumer submits an affidavit of his no fault when it is suspected that the replacement is
attributable to consumer’s fault, then pending the checks to search the fact, the meter should be
replaced as if the replacement is not attributable to consumer’s fault and such time lines shall be
followed. However, if it is established later that the replacement is attributable to the consumer then no
claim what so ever will be entertained for the lack of service or non-compliance of SOP.
(4) The consumer must be shown the procedure and should be supplied with a copy of the fact finding
report whenever the causes of the replacement are established. Any technicality involved should, as far
as possible and practicable, be explained in simpler terms as far.
(5) When the replacement is attributable to the consumer for causes like tampering, connecting additional
unauthorized load then there is no compensation to be given though time lines for the replacement of
the meter are to be followed.
G Shifting of meters/Service lines (for Urban, Rural and Remote Areas)
Compendium of HPERC Regulations, March 2021 15
(i)
Notice of inspection on receipt
of application. /conveying
reasons for denial of request.
3 days. Rs. 50/- for
each day of
default
Not
Applicable
95% of
requests
received
(ii) Inspection after sending notice. 7 days.
(iii)
Issuance of demand note to the
applicant for payment of
estimated cost/charges.
10 days.
(a) shifting of meter/service
connection
7 days after the
deposit of cost.
(b) shifting of LT/HT lines 20 days after the
deposit of cost.
(c) shifting of transformer 30 days after the
deposit of cost.
H Period of scheduled outages
(Other than Load-shedding)
To be notified by
the licensee at
least 24 hrs. in
advance and shall
not exceed 12 hrs.
a day.
Rs. 50/- for
each default
Rs. 20/- for
each default
Min. 99%
I Voltage problems (for Urban, Rural and Remote Areas)
On receipt of a voltage fluctuation complaint, Licensee shall verify if the voltage fluctuation is
exceeding the limits specified and upon confirmation
(a) Voltage Fluctuations (provided no expansion/enhancement of the network is involved)
(1) Local problem -
in vicinity of consumer premises in
vicinity but extending through the
service line till the first pole
6 working hours
2 days
Rs. 10/- for
each hour
of default
beyond
maximum
specified
time limit
Rs.5/- for
each hour of
default
beyond
maximum
specified
time limit
Min. 95%
(2) Change of transformer tap 2 days
(3) Restoration of distribution lines/
transformer/capacitor
30 days
(b) Low voltage -
(1) Where expansion/enhancement of the
network is not involved
120 days from the
registration of the
complaint.
(2) Where expansion/enhancement of
the network is involved
120 days from the
registration of the
complaint.
(c) Where expansion/enhancement of the
network is involved
(i) Submission of proposal for
Commission’s approval
one month from
the registration of
complaint
(ii) Completion of erection /
commissioning of sub-station
Within the time
lines specified in
the capital
expenditure plan /
or the timelines
approved by the
Commission
16 Compendium of HPERC Regulations, March 2020
Note:-The compensation for industrial and agricultural consumers, who are expected to install capacitors at their
end, shall not be paid the compensation, if capacitors of adequate capacity are not installed at their premises.
J Change in contract demand (for Urban, Rural and Remote Areas)
(i)
Request for change in
Contract Demand.
30 days after
receipt of
application
Rs. 50 for each
day of default
Not applicable Min. 95%
(ii)
Refund of excess
amount, after making
adjustments for the
amounts outstanding
from the consumer to
the licensee,
Within one month
of the effective
date of reduction
of contract
demand/connected
load;
Rs.50 for each
day of default.
Not applicable Min. 95%
K Complaints about consumer bills (for Urban, Rural and Remote Areas)
On receipt of the
consumer billing
complaint.
Note- In case the
complaint is genuine
and revision of bill
already issued becomes
necessary, the due date
for payment of bill shall
be reckoned from the
date of revised bill for
the purpose of
disconnection of supply
or for levy of additional
charges for belated
payment.
twenty four hours
if no additional
information is
required.
Within ten days,
if additional
information is
required
Rs. 10/- for each
day of default
beyond maximum
specified time limit
Not
applicable
99% of complaints
received
L New connections/additional load (for Urban, Rural and Remote Areas)
Time lines for release of
new connections/
additional load *
* Submissions of PAC
along with A&A form
should not be insisted for
new connection/
additional load request up
to 100 kW.
As per the
HPERC
(Licensee’s
Duty for
Supply of
Electricity on
request)
Regulations,
2004.
LT Rs. 50 / day
11kV Rs.50/ day
22kV Rs. 50 / day
33kV Rs. 100 /
day EHT Rs.
400 / day
Not
Applicable
Min. 95%
M Transfer of Ownership and change of category (for Urban, Rural and Remote Areas)
(1) Transfer of
title/ownership
Within 10 days after
completion of
formalities
Rs. 100 for each
day of default
Not
Applicable
Min.99%
(2) Change of Category Within 10 days after
completion of
formalities
Rs. 100 for each
day of default
Not
Applicable
Min.99%
(3) Conversion between various voltage classes-
(a) Informing
feasibility
Within 7 days after
receipt of
application
Rs. 10 for each
day of default
Not
Applicable
Min. 95%
Compendium of HPERC Regulations, March 2021 17
(b) Conversion from
single phase to Low
Tension 3-phase and
vice-versa
Within two months
from the date of
payment of charges
and submission of
the test report.
Rs. 50 for each
day of default
Not
Applicable
Min. 95%
(c) Conversion from
Low Tension 3-phase
to High Tension 3-
phase and vice-versa
Rs. 50 for each
day of default
Not
Applicable
Min. 95%
(i) if extension of
line is not required
Within two months
from the date of
payment of Charges
and submission of
test report.
(ii) if extension of
line is required
Within 90 days from
the date of payment
of charges and
submission of test
report.
N Disconnection/Re-connection of supply (for Urban, Rural and Remote Areas)
(a) Consumer requesting
permanent
disconnection-
(i) special reading and
preparation of final
bill, including all
arrears up to the date
of such billing
within five days from
receipt of application
Rs. 50/- for each day of
default
Not
applicable
Min. 98%
(ii) disconnection of
supply
Within 3 days upon
payment of dues.
(iii) refund of the
security deposit, if
any, after making
adjustments for the
amounts outstanding
from the consumer to
the licensee.
Within one month of
the effective date of
termination of the
agreement
Rs. 50/- for each day of
default beyond
specified maximum
time limit in addition to
simple interest @12%
pa as specified under
the security deposits
regulation.
(b) Consumer requesting temporary disconnection-
special reading and
preparation of final
bill, including all
arrears up to the date
of such billing
Within five days from such
request
Rs. 50/- for each
day of default
beyond
specified
maximum time
limit
Not
applicab
le
Min. 95%
temporary
disconnection
within 5 days upon payment of
dues (including energy charges,
fix charges like demand
charges, meter rent etc. and
reconnection charges
(c) Reconnections-
18 Compendium of HPERC Regulations, March 2020
(i) after temporary
disconnection (if the
service line has been
removed)
Same as specified
for new
connection/addition
al load request
under item L of this
schedule.
Same as specified for new
connection/ additional load
request under item L of this
schedule.
Not
applicabl
e
(ii)
after temporary
disconnection (if the
service line has not been
removed)
Within 24 hours of
receipt of request.
Rs. 100/- per day of default Not
applicabl
e
Min. 99%
(iii)
where circumstances
leading to the
disconnection were
attributed to the
licensee.
within 1 day on
receipt of request /
complaint.
Rs. 300/- per day of default Not
Applicabl
e
100%
(d) reconnection of supply
disconnected under sub-
section(1A) of section
135 of the Act.
Within 48 hours
from the date of
deposit or payment
of assessed amount
or electricity
charges in
accordance with the
Act.
- - -
O Power Availability Certificate (for Urban, Rural and Remote Areas)
(provided all the
formalities as per clause
3.2 of the Supply Code
are met with and there is
capacity available with
the licensee)
Within forty five days of
the receipt of request or
such extended period as
approved by the
Commission
Rs. 50 for each
day of default
Not Applicable Min. 95%
P Temporary supply of Power (for Urban, Rural and Remote Areas)
(a)
Examination the
technical feasibility of
the connection
requested for and if
found feasible
sanctioning the load and
raising a demand note -
Within 3 days of receipt
of the application and
payment of chargers.
Rs. 50/- per day of
default
Not
Applicable
Min. 95%
(b)
Release of temporary
connection –
(i) Where no extension
of distribution mains
or the commissioning of
new sub-station is
involved.
(ii) Where extension of
distribution mains or
the commissioning of
new sub-station is
involved.
Within 7 days from the
receipt of application
and payment of
charges.
Within the time lines as
specified in the HPERC
(Licensee’s Duty to
Supply of Electricity on
request) Regulation,
2004.
LT Rs. 50 /day
11kV Rs. 50/ day
22kV Rs.50/ day
33kV Rs.100/day
EHT Rs.400/ day
Not
applicable
Min. 95%
Q Other Standards (for Urban, Rural and Remote Areas)
(a)
Making and keeping
regular appointments
a) At Sub-Divisional
Level
Rs. 20/- per
default
Not
Applicable
Min. 95%
Compendium of HPERC Regulations, March 2021 19
-Twice a week
b) At Divisional Level
- Once a week
c) At Circle Level
-Once a fortnight
d) At Chief Engineer
Level
-Once a month
Note:
1) Days and time of
appointments should be
notified by the licensee
on uniform basis for all
offices throughout the
State.
2) Days and time of
appointment shall be
displayed outside the
room of the Officer
concerned and also
printed on the backside
of the bills.
Rs. 50/- per
default
Rs. 100/- per
default
Rs. 200/- per
default
(b) Making and keeping
special appointments
Appointments may be
had at the above levels at
the specific request of
any consumer
Rs. 200 per
default
Not
Applicable
Min. 98%
(3) Efficiency Parameters
Parameters Targeted Level of Standard of Performance
(a) Failure of -
(i) 33/11 kV Power
Transformers
(ii) 11/0.4kV
Distribution Power
Transformers
Not exceeding 0.5% in a year of the number of transformers in service
at the beginning of year
Not exceeding 5% in a year of the number of transformers in service at
the beginning of year
(b) % of Stopped/
Defective Meters
Not exceeding 2 % of the meters installed
(c) % T& D Losses Subject to Commission’s directions in ARR/Tariff Order from time to
time
(d) % Collection
Efficiency
Overall Annual Average monthly collection efficiency not less than
99%
LT Consumers Overall Annual Average monthly collection efficiency
not less than – 95%
HT & EHT consumers Overall Annual Average monthly collection
efficiency not less than – 100%
Where monthly collection efficiency = Amount realized divided by the
amount assessed during the month.
Bills challenged in any court of law shall not be considered for the
purpose of collection efficiency.
20 Compendium of HPERC Regulations, March 2020
(4) Reliability & Quality of Power Supply
(I) Reliability of the distribution system operated by the licensee shall be computed on
the basis of number and duration of sustained interruptions in pre-defined period of time
e.g. quarterly, annually etc. In a power system, it may take a few minutes or repetitive
operation of protective devices, to restore power after transient faults or to reroute
power in the network to restore supply to the affected area.
The licensee shall compute and report the value of following sustained interruption
indices, prescribed by the Institute of Electrical and Electronics Engineers (IEEE)
Standard 1366 of 2003, from
1
[“1
st
April, 2012”] and till then, the methodology for
calculation of reliability indices shall continue as specified under the Himachal Pradesh
Electricity Regulatory Commission (Distribution Licensees' Standards of Performance)
Regulations, 2005):
Sustained interruptions, not classified as a part of momentary event, which last more
than five minutes duration shall be considered for judging the reliability of the system
and momentary interruptions (including all reclosing operation that occur within five
minute of the first interruption), not exceeding five minutes duration, from the first
interruption shall be ignored in computation.
a. SAIFI
SAIFI (System Average Interruption Frequency Index) indicates how often the
average customer experiences a sustained interruption over a pre-defined period of
time. Mathematically, this is as follows,
SAIFI= Σ Total Number of Consumers Interrupted
Total Number of Consumers served
i.e. SAIFI = Σ Ni
NT
Where, Ni = No. of interrupted consumers for each sustained interruption
event during a quarter.
NT = Total no. of consumers served in the area.
b. SAIDI
SAIDI (System Average Interruption Duration Index) indicates the total
duration of interruption for an average consumer, as consumer minutes or
consumer hours, during a pre-defined period. Mathematically, this is as
follows,
SAIDI= Σ Customer Interruption Durations
Total Number of Customers Served
i.e. SAIDI = Σ ri Ni
NT
ri = Restoration time for each interruption event
Ni = No. of interrupted consumers for each sustained interruption
event during the quarter.
NT= Total no. of consumers served in the area.
c. Consumers Average Interruption Frequency Index (CAIFI)
1 Subs. for “1st April, 2011” vide Not. No. HPERC/ 401 dated 30th April , 2011 published in the R H.P dated
2nd May 2011 at p 560-561.
Compendium of HPERC Regulations, March 2021 21
Consumers average interruption frequency index gives the average frequency of
sustained interruptions for those consumers experiencing sustained
interruptions. The consumer is counted once regardless of the number of times
interrupted for this calculation.
CAIFI = Σ Ni
CN
Where
Ni = Total no. of interrupted consumers for each sustained interruption
event during the quarter.
CN = Total number of consumers who have experienced a sustained
interruption during the quarter.
d. Consumers Average Interruption Duration Index (CAIDI)
Consumers average interruption duration index is the average time required to
restore service. Mathematically, simplified
CAIDI = SAIDI / SAIFI
-CAIDI shall be calculated for a sub-station, for a circle and for the
Licensee as a whole. The index shall be expressed in interruption minutes
per consumer per year.
-SAIFI, SAIDI, CAIFI and CAIDI indices shall be calculated for a
sub-station, for a circle and for the Licensee as a whole quarterly and the
consolidated indices value should form part of the report under sub-
regulation 10(1).
While the indices, the following types of interruptions shall not be taken
into account:
(a) Planned outages i.e. interruption due to “State Annual Outage plan”
prepared in advance for the financial year SLDC if not deferred
taking into account the statutory requirements ( Clause 5.8.4 (f) of the
State Grid Code)
(b) Momentary interruptions of duration less than five minutes
(c) Contingency outages in intra-State transmission network as identified
under clause 3.5.1 (a)of the State Grid Code.
(d) Outages due to Force Majeure reasons beyond the control of the
Licensee like fire, earthquake, floods, storms, and riots etc. including
forced outages i.e. an outage of a generating unit or a transmission
facility due to a fault or other reason which has not been planned.
Within six months of these regulations coming into force, the Licensee shall
declare Reliability Index (RI) in the form of SAIDI & SAIFI in its area of
supply and shall publish it in local newspaper having wide circulation in
that area.
The Commission shall fix benchmarks for standards of reliability on the
basis of data collected for one year and revise the levels to be achieved from
time to time for ensuring improvement in the performance of the licensee.
(II) Voltage Variation Limits
22 Compendium of HPERC Regulations, March 2020
Licensee shall ensure that long duration voltage variation at the point of commencement of
supply to consumer as defined in Indian Electricity Rules, 1956, shall not vary from the
declared voltage as below:
Type of supply and declared voltage Variation maximum
limit % (+)
Variation
Minimum limit
% (-)
230 Volts single phase 50 Hz AC supply 6% of declared voltage 6% of declared
voltage
400 Volts three phase 50 Hz AC supply 6% of declared voltage 6% of declared
voltage
2200/6600/11000/15000/22000/330000
Volts three phase 50 Hz AC supply
6% of declared voltage 9% of declared
voltage
66000 Volts and above three phase 50 Hz
AC supply
10% of declared voltage 12.5% of declared
voltage
The complaints with respect to voltage variation limits shall be established through
portable voltage recorders or meter reading instruments.
(III) Voltage unbalance
The Voltage unbalance shall not exceed the following limits:
Voltage Level Limit of voltage
unbalance
Implementation Stage
33 kV level 3% As specified by CEA Grid Connectivity
Regulation, 2004
11 kV/22 level 3.5% As specified by CEA Grid Connectivity
Regulation, 2004
Annexure-A
(see sub-regulation (2) of regulation 5)
APPLICATION FOR CLAIMING COMPENSATION AMOUNT
BY THE AFFECTED CONSUMER
1 Name of the Consumer
2 Address
3 Nature of complaint in brief
4 Complaint Number
5 Date and time of Registration of complaint
6 Date and time the complaint was attended to by the Licensee
Compendium of HPERC Regulations, March 2021 23
7 Standard time within which the complaint is to be attended to
as per Licensees’ Standards of Performance Regulations
8 Actual Time taken to attend to the complaint
9 Compensation claimed as per Licensees’ Standards of
Performance Regulations
Date:
Place: Signature
ACKNOWLEDGMENT
Claim Number:
Date
Name of the Consumer
Claim for compensation amount received on (Date)
Signature of the official receiving the application
With Name, Seal and Date
Previous and next
Questions people ask
Is regulation 18 of the Himachal Pradesh Electricity Regulatory Commission (Distribution Performance Standards) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Distribution Performance Standards) Regulations, 2010 is recorded.