Regulation 12, The Himachal Pradesh Electricity Regulatory Commission (Distribution Performance Standards) Regulations, 2010: Auditing Methodology
The Himachal Pradesh Electricity Regulatory Commission (Distribution Performance Standards) Regulations, 2010 - Regulation 12
Text of regulation 12
Auditing Methodology
12. Auditing Methodology .- (1) The information obtained, under sub-regulation (1) of
regulation 11, vis-à-vis information supplied by the licensee under regulation 10, shall
be graded in two parts - reliability and accuracy of the data as under:-
I Reliability
Grade
Assessment of reliability Grade
A Based on proper records with adequate procedures
B Data has significant procedural deviations
C Unsatisfactory data
II Accuracy Grade Accuracy
Grade
Level
Percentage of compensation paid to be
recovered through ARR for each
parameter circle wise*
1 +/-2% 100%
2 +/-5% 85%
3 +/-10% 70%
Compendium of HPERC Regulations, March 2021 9
* subject to achievement of overall standard of performance for respective parameter
Only if reliability of data is established (at least Grade A), further analysis will be carried
out for claims of accuracy of data for each parameter (excluding those where the overall
standards of performance has not been achieved) on circle wise basis and subsequently the
amount of total compensation so paid out in respect of each parameter on circle basis shall
be considered as a pass through in ARR as stipulated above.
(2) The provisions contained in sub-regulation (1) shall be effective from 1
st
April
2011.
(3) Where the commission considers it expedient, so to do, it may, by order in
writing, call upon the licensee to furnish in writing such information as may be necessary
for the enforcement of the provisions of sub-regulation (1) of this regulation.
(4) Till 1
st
April, 2011 when the provisions under sub-regulation(1) become
effective, the compensation paid, by the licensee under regulation 5, for the respective
parameters computed circle wise, may be allowed to be recovered, partly or fully, in the
revenue requirement of licensee, keeping in view the extent to which the licensee is able to
achieve the overall standards of performance, as measured through auditing results or
investigation carried out under these regulation:
Provided that the compensation paid by the licensee, which is attributed to
negligence, inefficiency and for not exercising reasonable care and diligence by its
employees would not be allowed as pass-through in the ARR of the licensee.
Previous and next
Questions people ask
Is regulation 12 of the Himachal Pradesh Electricity Regulatory Commission (Distribution Performance Standards) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Distribution Performance Standards) Regulations, 2010 is recorded.