9. Implementation arrangements.-(1) Each Operation Circle Unit of the licensee shall
be treated as a responsibility centre for overall performance of standards specified under
these regulations. The officer heading the responsibility centre shall have total
accountability and associated responsibility and authority for managing the actions and
performance of the responsibility centre.
(2) The operational head of the licensee shall have overall responsibility for
implementation of standards of performance and he shall, to bring in the sense of
ownership and competition, set the performance parameters as well as benchmarks for
improvement for each responsibility centre. The operational head of the licensee shall
establish one control centre at the head office under an officer not below the rank of the
Superintending Engineer for compilation, evaluation, ranking and analyzing the
performance of responsibility centers.
(3) Immediately after the commencement of these regulations, and under
intimation to the Commission, but not later than 30 days, the control centre shall develop
uniform formats for data collection, compilation and evaluation of performance of the
responsibility centers. The control centre shall prepare and circulate the procedures for
compilation and computation of various standards and performance indicators (reliability
indices and efficiency parameters) along with uniform definitions and explanations of
terms used for unambiguous interpretation by all the responsibility centers.
(4) The control centre shall monitor, evaluate, rank the circles and advise the
responsibility centers for corrective measures. A quarterly report on progressive monthly
improvements made by the responsibility centre shall be prepared by the control centre.
Compendium of HPERC Regulations, March 2021 7
Explanation.- For the purpose of this regulation the expression “Operational head”
shall mean and include the officer heading the distribution Wing of the licensee.
CHAPTER- IV
SUBMISSION OF REPORTS
Previous and next
Questions people ask
Is regulation 9 of the Himachal Pradesh Electricity Regulatory Commission (Distribution Performance Standards) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Distribution Performance Standards) Regulations, 2010 is recorded.