Bulk head and air-locks
127. Bulk head and air-locks.—The employer shall ensure at a
construction site of a building or other construction work that,—
(a) a bulk head or air tight diaphragms retaining compressed air, when
used within a tunnel or a shaft, is constructed to withstand the
maximum pressure at one point two five times the maximum working
pressure of such bulk head or diaphragm and such bulk head or
diaphragm is tested before its each use by a responsible person
referred to in rule 91, to ensure that such bulk head or diaphragm is
in proper working order ;
(b) such responsible person keeps the record of each test referred to in
clause(a) and such records are produced for inspection to the
Inspector having jurisdiction on demand ;
(c) the bulk head and the diaphragm referred to in clause (a) are made of
good quality material of adequate strength and are able to withstand
the maximum pressure on which they are subjected to at any time of
their use ; and
(d) bulk-head anchorage and air lock are tested at their work place at an
excavation or tunnelling work immediately after their installation at
such place.
Previous and next
Questions people ask
Is rule 127 of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 still in force?
No repeal of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 is recorded.