Rule 66, Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008: General provisions regarding use of concrete
Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 - Rule 66
Text of rule 66
General provisions regarding use of concrete
66. General provisions regarding use of concrete.—The employer
shall ensure at a construction site of a building or other construction work that,—
(a) all construction with the use of concrete or reinforced
concrete are based on plans as—
(i) include specifications of steel and concrete and other
material to be used in such construction;
(ii) give technical details regarding methods for safe
placing and handling of such materials as specified in
sub-clause (i);
(iii) indicate the type, quality and arrangement of each part
of a structure of such construction; and
(iv) explain the sequence of steps, to be taken for
completion of such construction;
(b) form work and shores, used for concrete work, are
structurally safe and are properly braced or tied together so
as to maintain position and shape of such form work or
shores; and
(c) form work structure, used for concrete work, has sufficient
cat-walks and other secured access for inspection of such
structure, if such structure is in two or more tiers.
Previous and next
Questions people ask
Is rule 66 of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 still in force?
No repeal of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 is recorded.