Rule 35, Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008: Hoists
Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 - Rule 35
Text of rule 35
Hoists
35. Hoists.—The employer shall ensure at a construction site of a building
or other construction work that,—
(a) hoist towers are designed according to the relevant national
standards;
(b) hoist shafts are provided with rigid panels or other adequate
fencing—
(i) at the ground level on all sides of such shafts; and
(ii) at all other levels on all sides of the access to such shafts;
(c) the walls of hoist shafts, except at approaches, extend at least
one and a half metre above the floor or platform of access to
such shafts;
(d) approaches to a hoist are provided with gates which are—
(i) girded to maintain visibility;
(ii) at least of two metres height; and
(iii) equipped with a device, which requires such gate to be
closed before the platform of such hoist can leave the
landing and prevents the gate from being opened, unless
such platform, is at the landing;
(e) approaches to a hoist are adequately lit;
(f) the guides of hoist platforms offer sufficient resistance to
bending and to buckling in case of jamming, by providing a
safety catch;
(g) overhead beams and their supports are capable of holding the
Section 40 (2) (e)
26
total maximum live and dead loads that such beams and supports
will be required to carry, with a safety factor of at least five;
(h) a clear space is provided—
(i) above the highest stopping place of cage or platform to
allow sufficient unobstructed travel of such cage or
platform in case of over winding; and
(ii) below the lowest stopping place of such cage or platform;
(i) adequate covering is provided above the top of hoist shafts to
prevent materials from falling into such shafts;
(j) outdoor hoist towers are erected on adequately firm foundation
and are securely braced, guided and anchored;
(k) a ladder way extends from the bottom to the top of every outdoor
hoist tower, in case no other ladder way exists within easy
reach and such ladder ways, comply with the relevant national
standards;
(l) the rated capacity of a hoisting engine is at least one and a half
times the maximum load that such engine will be required to
move;
(m) all gearings on a hoisting engine are securely enclosed;
(n) steam piping of a hoisting engine is adequately protected against
accidental contact of such piping with the building workers;
(o) electrical equipment of a hoisting engine is effectively earthed;
(p) a hoist is provided with suitable devices to stop a hoisting engine
as soon as the platform of such hoist reaches its highest
stopping place;
(q) a hoisting engine is protected by a suitable cover against weather
and falling objects;
(r) a hoisting engine set up in a public thoroughfare is completely
enclosed;
(s) all exhaust steam pipes discharge steam in such a manner that
the steam so discharged does not scald any person or obstruct
the operator’s view;
(t) the motion of a hoist is not reversed without first bringing it to
rest to avoid any harm from such reverse motion;
(u) a hoist, not designed for the conveyance of persons, is not set
27
in motion from the platform of such hoist;
(v) pawl and ratchet wheels of a hoist, requiring disengagement of
such pawls from such ratchet wheels before the platform of
such hoist is lowered, are not used;
(w) a platform of a hoist is capable of supporting such maximum
load that such platform may carry with a safety factor of at
least three;
(x) a platform of a hoist is equipped with suitable safety gear, which
can hold such platform with its maximum load in case the
hoisting rope breaks;
(y) on platform of a hoist, the wheelbarrows or truck are efficiently
blocked in a safe position;
(z) a cage of a hoist or a platform, where the building workers are
required to enter into such cage or to go on such platform at
landing level, is provided with a locking arrangement to prevent
such cage or platform from moving during the time a building
worker enters or leaves such cage or platform;
(za) the sides of a platform of a hoist, which are not used for loading
or unloading, are provided with toe-board and enclosures of a
wire mesh or any other suitable means to prevent the fall of
any part of a load from such platform;
(zb) a platform of a hoist, which has any probability of falling any
part of load from it, is provided with an adequate covering
with such fall;
(zc) the counter-weights of a hoist consisting of an assemblage of
several parts are so constructed that such parts are rigidly
connected together;
(zd) the counter-weight of a hoist run between guides;
(ze) at every level of work, the building workers are provided with
adequate platforms for performing such work; and
(zf) a legible notice in English, Punjabi and also in Hindi or the local
language, understood by majority of the building workers, is
displayed at—
(i) a conspicuous place of the platforms of a hoist and that
such notice states the maximum carrying capacity of such
hoist in kilograms;
28
(ii) a conspicuous place on the hoisting engine and that such
notice shall state the maximum lifting capacity of such
hoist in kilograms;
(iii) a conspicuous place on a hoist authorised and certified
for the conveyance of the person on the platform or cage
and such notice states the maximum number of persons
to be carried on such hoist at one time; and
(iv) a conspicuous place on a hoist carrying goods and other
materials and such notice states that fuel hoist is not meant
for carriage of persons.
Previous and next
Questions people ask
Is rule 35 of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 still in force?
No repeal of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 is recorded.