Rule 29, Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008: Winches
Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 - Rule 29
Text of rule 29
Winches
29. Winches.—The employer shall ensure at a construction site of a
building or other construction work that,—
(a) (i) winches are not used, if control levers operate with
excessive friction or play;
(ii) double gear winches are not used unless a positive means
of locking the gears shift is provided;
(iii) there is no load, other than the one, being lifted and the
hook assembly on the winch while changing gears on a
two gear winch;
(iv) adequate protection is provided to winch operator against
abnormal weather;
(v) temporary seats or shelters for winch operator, which may
pose hazard to the winch operator or any other building
worker, are not allowed to be used; and
(vi) control levers are secured in the neutral position and,
whenever, possible, the power is shut off whenever
winches are left unattended;
(b) in use of every steam winch—
(i) measures are taken to prevent escaping steam from
obscuring any part of the construction site or other work
place or from otherwise hindering or injuring any building
worker;
(ii) extension control levers, which tend to fall of their own
weight, are counter balanced;
(iii) winch operators are not permitted to use the winch control
extension levers except for short handles on wheel type
controls and that such levers are of adequate strength,
secure and fastened with metal connections at the fulcrum
and at the permanent control lever;
(c) in use of every electric winch, a building or other construction
worker is not permitted to transfer, alter or adjust electric
control circuits in case of any defect in such winch; and
Section 40 (2) (e)
22
(d) electric winches are not used for building work where—
(i) the electro-magnetic brake is unable to hold the load; or
(ii) one or more control points, either hoisting or lowering, are
not operating properly.
Previous and next
Questions people ask
Is rule 29 of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 still in force?
No repeal of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 is recorded.