Rule 9, Rajasthan Land Revenue (Conversion of agricultural land for non-agricultural purposes in rural areas) Rules, 2007: Prescribed Authority for conversion
Rajasthan Land Revenue (Conversion of agricultural land for non-agricultural purposes in rural areas) Rules, 2007 - Rule 9
Text of rule 9
Prescribed Authority for conversion
9. Prescribed Authority for conversion.-
63
[(1)
64
[A khatedar tenant/ group of
khatedar tenants], seeking permission for conversion of agricultural land for any non-
agricultural purpose shall submit an application online to the authority prescribed below in
Form-A along with the documents specified therein
63a
[and a copy of receipt as proof of the
payment of amount of application fee Rs. 2000/- for residential unit purpose and Rs.20,000/-
for any other purpose. Application fee shall not be refunded and it shall not be adjested in
conversion charges]
64 a
[and a hard copy of complete application shall also be submit within 7
days to the prescribed authority]:
63a
[Purpose of
Conversion
Prescribed Authority
(a) Residential unit. Tehsildar upto
1000 Square meters.
(b) Residential Colony/
project
(i) Sub Divisional Officer- Where total area does not
exceed 10,000 square meters.
(ii) Collector- Where total area does not exceed
50,000 square meters.
(iii) Divisional Commissioner- Where total area does
not exceed 1,00,000 square meters.
(iv) State Government- Where total area exceeds
1,00,000 square meters.
62
Substituted by Notification no. F.9(56)rev-6/20/57/, dated 17.08.20
62a Added by Notification no F.9(35)rev-6/2024/30, dated 04-12-2024
63
Substituted by Notification no. F.6(6)rev-6/14/33, dated 06-10-16
63a
Inserted by Notification no. F.6(26)rev-6/14/28 ,dated 29.04.26
64
amended by Notification no. 6(26)Rev-6/2014Pt./30, dated 30-03-21
64a amended by Notification no.F.1(4)Rev-9/2020/25, dated 22-11-2024
(c) Commercial purpose (i) Sub Divisional Officer- Where the total area does
not exceed 5000 square meters (but excluding
cinema, petrol pump, explosive magazine,
multiplex, hotel, resort).
(ii) Collector- All cases of commercial purposes
where the total area does not exceed 50,000 square
meters.
(iii) Divisional Commissioner- Where total area does
not exceed 1,00,000 square meters.
(iv )State Government- Where the total area of land
exceeds 1,00,000 square meters.
(d) Industrial Area/
Industrial purpose
(i) Sub Divisional Officer - Where total area does not
exceed 10,000 square meters (but excluding
tourism unit)
(ii) Collector-Where total area does not exceed
1,00,000 Sqaure meters including tourism unit
(iii) Divisional Commissioner- Where total area does
not exceed 2,00,000 square meters
(iv) State Government - All cases where the total area
exceeds 2,00,000 Sqaure meters.
(e) Salt manufacturing
purpose
(i) Sub Divisional Officer - Where total area does not
exceed 1,00,000 square meters
(ii) Collector- Where total area does not exceeds
2,00,000 square meters.
(iii) Divisional Commissioner- Where total area
exceed 2,00,000 square meters
(f) Public Utility
purpose
(i) Sub Divisional Officer - Where total area does not
exceed 10,000 square meters.
(ii)Collector- Where total area does not exceed 50,000
square meters
(iii) Divisional Commissioner- Where total area does
not exceed 1,00,000 square meters
(iv)State Government- Where total area exceeds
1,00,000 square meters.
(g) Institutional purpose
and Medical
facilities
(i) Sub Divisional Officer- Where the total area does
not exceed 10,000 square meters
(ii)Collector- Where total area does not exceed 50,000
square meters.
(iii) Divisional Commissioner- Where total area does
not exceed 1,00,000 square meters
(iv)State Government-Where total area exceeds
1,00,000 square meters.
(h) SEZ
State Government
(i) Food Processing
unit
(i) Sub Divisional Officer - Where total area does not
exceed 10,000 square meters.
(ii)Collector- Where total area does not exceed
50,000 square meters
(iii) Divisional Commissioner- Where total area does
not exceed 1,00,000 square meters
(iv)State Government- Where total area exceeds
1.00,000 square meters.
(j) Renewable Energy
Projects
(i) Sub Divisional Officer - Irrespective of area for
conversion of land, held by khatedar tenant who is
member of Scheduled Cast or Scheduled Tribes.
Provided that, if Sub Divisional Officer fails to
decide the application within fifteen days from the
date of application, the application shall be
forwarded to Collector who shall either issue an
order of conversion in Form-B or inform the
application of the rejection of the application
within fifteen days.
(ii) Tehsildar-Irrespective of area for conversion of
land, held by khatedar tenant who is member of
Scheduled Cast or Scheduled Tribes.
Provided that, if Tehsildar fails to decide the
application within fifteen days from the date of
application, the application shall be forwarded to
Collector who shall either issue an order of
conversion in Form-B or inform the application of
the rejection of the application within fifteen
days.]
(k)Hydrocarbon
exploration.
Collector
(l)Stadium, play
ground and sports
complex
Collector
(m)Intergrated
Township
State Government
Provided that if residential colonies/projects are being set up on the Khatedari land
situated partially under the jurisdiction of urban bodies and its peripheral belt and partially
under rural area, then the conversion of Khatedari lands shall be done by the appropriate
competent officers authorized by the State Government under section 90-A of the Act and the
rate of conversion shall be charged for the whole area according to the rates specified by
Urban Development and Housing Department for the Urban areas and the conversion charges
charged for the land falling under the rural area shall be deposited in the Government
Revenue Head through challan.]
65
(2) For setting up of residential colonies/projects in rural area, 40% of total land shall be
reserved for public facilities including roads and remaining 60% land shall be utilized for
residential colonies/projects including 5% area of total land for commercial and institutional
purpose. The conversion charges at the rate of residential colony/project shall be payable on
the total area of the residential colonies/projects
66
[and for the purpose of integrated township
in rural area 40% of total land shall be reserved for public facilities including roads and the
conversion charges at the rate of integrated township shall be payable on the total area of the
integrated township].
71a
[For setting up of industrial area/industrial estate in rural area 70% area of
total land shall be reserved for setting up of industries out of which 3% area of total land may be
allowed to use for commercial purposes and the remaining 30% area of land shall be reserved for
open area, pulbic facilities including roads and essential welfare and supporting activities out of which
5% area of total land for open area, 15% area of total land for public facilities including roads and
10% area of total land for essential welfare and supporting activities shall be reserved. The conversion
charges, at the rate prescribed for the conversion of industrial area/industrial estate, shall be payable
on the total area of the industrial area/ industrial estate.]. The layout plan/building plan/certificate
of completion of the project for
67
[residential colony/project/ industrial area/industrial estate/
integrated township/tourism unit] in rural areas shall be approved
68
[by a committee
consisting of the following:-
(A) in case where the prescribed authority is Collector or the State
Government:-
1. District Collector Chairperson
2. Additional District Collector
(Administration) Member Secretary
3. Sub Divisional Officer concern Member
4. Executive Engineer posted in Zila Parishad Member
5. Zonal Senior Town Planner/Deputy Member
Town Planner of the Town Planning
Department
(B) in case where the prescribed authority is up to the rank of Sub-
divisional Officer:-
1. Sub-divisional Officer Chairperson
2. Tehsildar concern Member
3. Deputy Town Planner
of the Town Planning Dept Member”]
The Committee shall approve the lay out plan if it fulfills the conditions
mentioned above and it has an approach-way to the project not less than 30 feet in the width
and such approved lay out plan shall be part of the conversion order.
69
[No lay out plan is
65
Substituted by Notification no. F.6(6)rev-6/14/33, dated 06-10-16
66
inserted by Notification no. 6(26)Rev-6/2014Pt./30, dated 30-03-21
71a
inserted by notifaction no.F.no.9(35)rev.6/2021/79, dated 13.09.21
67
substitued by Notification no. 6(26)Rev-6/2014Pt./01, dated 04-01-22
68
substituted by Notification no. 6(26)Rev-6/2014Pt./50, dated 29-06-21
69
Inserted by Notification no. F.6(26)rev-6/2014/89, dated 13.10.20.
required to be approved for any other purpose but recorded approach way which is not less
then 15 feet in the width to the proposed land is required]:
70
[Provided that] once an applicant is allowed to convert his land for
industrial purpose in a district, he shall be allowed to convert other piece of khatedari
land for the same industrial purpose or its expansion in the same district only if the
existing industry for the same purpose is running.
71
[Provided also that] no application for conversion shall be required where
tenant desires to establish a micro, small scale industrial unit, kjawa (small brick kiln),
or desire to use of land for institutional purpose, medical facilities purpose or public
utility purpose on his own khatedari land upto an area not exceeding one acre
72
[or in
case of food processing unit not exceeding ten hectare and] such land shall be deemed
to have been converted for such a micro, small scale industrial unit, kjawa (small
brick kiln), institutional purpose, medical facilities or public utility purpose
73
[or food
processing unit]. No conversion charges shall be payable for such conversion.
Provided also that no application for conversion shall be required, if the
entire piece of land and building constructed thereon is to be used exclusively for
setting up of Information Technology Industry with the permission of Empowered
Committee on Investment chaired by the Chief Secretary. However, the conversion
charges shall be payable under these rules.
Provided also that in case of heritage hotels, if parking arrangement is made
available by the owner in premises or elsewhere, the requirement of width of
approach road shall not be applicable.
73a
[Provided also that in case of conversion of land for renewable power
projects held by khatedar tenant, no recorded approach way shall be required for issue
of conversion order, however khatedar shall himself certify, while applying for
conversion, that he has an approach way to his proposed land.]
"[(3) Prescribed authority upto the rank of Divisional Commissioner shall on
the receipt of the completed application along with documents prescribed therein,
examine and ensure whether land is not fall under any of the categories as specified in
rule 4 of these rules and after making such other enquiry, which he considers
necessary if he finds that such land is suitable for conversion he shall intimate
applicant to deposit the required amount of the conversion charges within 7 days. If
land is not found suitable for conversion, the application for conversion shall be
70
Substituted by Notification no. F.6(26)Rev-6/2014Pt./88, dated 17-05-22
71
Substituted by Notification no. F.6(26)Rev-6/2014Pt./88, dated 17-05-22
72
Inserted by Notification no. F.6(6)rev-6/2014/14, dated 08-02-19
73
Inserted by Notification no. F.6(6)rev-6/2014/14, dated 08-02-19
73a
substituted by Notification no. F.6(26)rev-6/14/28 ,dated 29.04.26
rejected and applicant shall be informed accordingly. After depositing of conversion
charges, prescribed authority shall issue an order of conversion in Form-B within 30
days from the date of receipt of completed application. If applicant fails to deposit
required conversion charges within stipulated period the application of conversion
shall be rejected. In case any khatedari tenant/group of khatedari tenants submits
complete application electronically in single window System Portal and same shall be
disposed off as per the provisions of the Rajasthan Enterprises Single Window
Enabling and Clearance Rules, 2011:
Provided that in case where conversion charges are exempted for conversion
of land of any purpose under these rules, prescribed authority finds that such land is
suitable for conversion, he shall issue conversion order within 30 days from the ate of
receipt completed application.
Provided further that no such order of conversion or regularisation shall be
passed by the prescribed authority where the application relates to agricultural land
falling within the revenue villages of Oria, Utaraj, AornaJawai, Achalgarh and
Salgaon of Tehsil Abu-Road of District Sirohi without prior approval of the State
Government."; and]
(4) deleted by Notification no. F.6(26)rev-6/14/28 ,dated 29.04.26
74
(5) In case the prescribed authority fails to issue an order under sub-rule (3) or (4) within
the specified period, he shall be liable for disciplinary action under relevant rules, where
conversion order is to issued by prescribed authority up to the rank of Sub Divisional Officer
within the prescribed period and application is complete in all respect then the Collector shall
pass necessary order regarding conversion within 30 days and in case prescribed authority is
Collector then the Divisional Commissioner shall pass necessary order regarding conversion
within 30 days. Such orders shall be deemed to have been passed by the prescribed authority
in exercise of its power vested under sub-rule (3) or (4), as the case may be.
(6) In cases where the State Government is the prescribed authority, the State Government
may, after the receipt of completed application along with documents prescribed therein, after
making necessary enquiry issue an order of conversion in form 'B' and inform the applicant
about rejection of the application or the balance amount of premium. If amount of balance of
premium is deposited within 15 days and copy of challan indicating amount of balance of
conversion charges submitted to State authority he shall issue an order of conversion in Form
'B'.
75
[ In case any
76
[khatedar tenant/ group of khatedar tenants] submits complete application
electronically in single window System Portal, it shall be disposed as per the provisions of the
Rajasthan Enterprises Single Window Enabling and Clearance Rules, 2011.]
74
Notification no. F.6(6)rev-6/14/33, dated 06-10-16
75
Added by notification no. F.6(26)rev.6/14/9, dated 29-04-15.
76
substituted by Notification no. 6(26)Rev-6/2014Pt./30, dated 30-03-21
77
(7) [In areas notified by the state government as "agro processing regions," for conversion
of land for setting up of non-polluting agro-processing industries, no examination shall be
required for suitability of land. The conversion order shall be issued after verification of land
title within two weeks of depositing of requisite conversion charges and documents of title.]
78
(8) [Notwithstanding anything contained in sub-rule (3), (4), (5) and (6) if the prescribed
authority, fails to dispose off the application of conversion of land for the establishment of
tourism unit as defined in clause (r) of sub-rule (1) of rule 2 within 45 days of the receipt of
the
completed application along with required documents, then such land shall be deemed
converted.]
79
Previous and next
Questions people ask
Is rule 9 of Rajasthan Land Revenue (Conversion of agricultural land for non-agricultural purposes in rural areas) Rules, 2007 still in force?
No repeal of Rajasthan Land Revenue (Conversion of agricultural land for non-agricultural purposes in rural areas) Rules, 2007 is recorded.