Rule 8, The Rajasthan Land Revenue (Allotment of waste land for bio-fuel plantation and bio-fuel based Industrial and processing unit) Rules, 2007: Application for Allotment of land
The Rajasthan Land Revenue (Allotment of waste land for bio-fuel plantation and bio-fuel based Industrial and processing unit) Rules, 2007 - Rule 8
Text of rule 8
Application for Allotment of land
8. Application for Allotment of land .- (1) Every person other than Companies
and Government Undertakings shall submit an application to the District Collector and
Companies and GovernmentUndertakings shall submit an application to the State
Government, in Form-'A'. alongwith following documents in triplicate duly signed by the
applicant:-
(a) Site Plan of the wasteland;
(b) Project Report;
(c) Building Plan of bio-fuel based industrial purpose processing unit, if any;
(d) Copy of bye-laws, articles of association or partnership deed (wherever is
applicable).
(2)Application by Companies, Public Undertakings and Societies shall be
accompanied by a registration fee of Rs. 1000/- and security amount equal to Rs. 400/-
per hectare. The security amount shall be adjustable on successful implementation of
the project.
Previous and next
Questions people ask
Is rule 8 of the Rajasthan Land Revenue (Allotment of waste land for bio-fuel plantation and bio-fuel based Industrial and processing unit) Rules, 2007 still in force?
No repeal of the Rajasthan Land Revenue (Allotment of waste land for bio-fuel plantation and bio-fuel based Industrial and processing unit) Rules, 2007 is recorded.