Rule 5, The West Bengal Municipal (Building) Rules, 2007: Further information required to be submitted by applicant
The West Bengal Municipal (Building) Rules, 2007 - Rule 5
Text of rule 5
Further information required to be submitted by applicant
5. Further information required to be submitted by applicant.—
Within fifteen working days from the date of receipt of an application for approval of building-site, the Municipal
authority may require the applicant—
(a) to furnish him with any information on matters referred to in these rules which has not already been given in the
documents thereunder; or
(b) to satisfy him that there are no objections which may lawfully be taken to the approval of the site.
Previous and next
← Rule 4Applications for approval of building sites and for permission to construct or reconstruct buildings other than hutsRule 6 →Incomplete or defective information
All provisions of The West Bengal Municipal (Building) Rules, 2007
Questions people ask
Is rule 5 of the West Bengal Municipal (Building) Rules, 2007 still in force?
No repeal of the West Bengal Municipal (Building) Rules, 2007 is recorded.