Rule 80, The Karnataka Municipalities Accounting and Budgeting Rules, 2006.: Measurement of works
The Karnataka Municipalities Accounting and Budgeting Rules, 2006. - Rule 80
Text of rule 80
Measurement of works
80. Measurement of works — (1) All works executed by the
Municipality shall be measured at least once in a month or at
such periodicity agreed upon in the contract and recorded in the
Measurement Book. On recording in the Measurement Book a
bill shall be raised.
Provided that, in the case of small works, the execution of
which runs over only a few days, works may be measured up
and paid once for all after their completion, and the agreements
with the contractors shall provide for this wherever applicable.
(2) Check measurements of works shall ordinarily be made as
early as possible after recording the measurements in the
Measurement Book. In no case, check measurements shall be
51
delayed for more than a period of two weeks from the date of
completion of the work.
Previous and next
All provisions of The Karnataka Municipalities Accounting and Budgeting Rules, 2006.
Questions people ask
Is rule 80 of the Karnataka Municipalities Accounting and Budgeting Rules, 2006. still in force?
No repeal of the Karnataka Municipalities Accounting and Budgeting Rules, 2006. is recorded.