252. Prohibition Order.-(1) If it appears to the Inspector that any site or place at which any
building or other construction work is being carried on, is in such condition that it is
dangerous to life, safety or health of building workers or the general public, he may in
writing, serve on the employer of building workers or on the owner of the establishment or on
the person in-charge of such site or place, an order prohibiting any building or other
construction work at such site or place until measures have been taken to remove the cause of
the danger to his satisfaction.
(2) An Inspector serving an order under sub-rule (1) shall endorse a copy to the Chief
Inspector of Inspection of Building and Construction
(3) Such prohibition order shall be complied with by the employer forthwith.
-100-
(4) Any person aggrieved by an order under sub-rule (1) may within 15 days from the
date on which the order is communicated to him, prefer an appeal to the Chief
Inspector of Inspection of Building and Construction or where such order is by
the. Chief Inspector of Inspection of Building and Construction to the Secretary to
the Government, Labour & Employment Department and the Chief Inspector of
Building and other Construction Work or the Secretary to the Government,
Labour & Employment Department, as the case may be shall, after giving the
appellant an opportunity of being heard, dispose of the appeal as expeditiously as
possible.
Provided that the Chief Inspector of Inspection of Building and
Construction or the Secretary to the Government, Labour and Employment
Department, as the case may be, may entertain the appeal after the expiry of the
said period of 15 days if he is satisfied that the appellant was prevented by
sufficient cause from filing the appeal in time.
Provided further that the prohibiting, shall be complied with, pending the
decision of the Chief Inspector of Inspection of Building and Construction or the
Secretary to Government, Labour and Employment Department.
Schedule-I
(See rule 56(a) and 71(a))
Manner of test and examination before taking lifting appliance, lifting gear and wire
rope into use for the first time.
Testloads
(1) Lifting appliances:-livery lifting appliance with its accessory gear, shall be subjected to a
test toad which shall exceed the safe working load (SWL) as specified in the following table:-
TABLE
Safe working load Test load
Upto 20 tonnes .. 25 per cent in excess of safe working load.
20 to 50 tonnes .. 5 tonnes in excess of safe working load.
Over 50 tonnes .. 0 percent in excess of safe working load.
-101-
(2) Lifting Gear:- (a) Every ring. hook, chain, shackle, swivel, eye-bolt, plate clamp,
triangular plate or pulley block (except single sheave block) shall be subjected to a test
load which shall not be less than the load as specified in the following table:-
TABLE
Safe working load
(in tonnes)
Upto 25
..
Test load
(in tonnes)
2 x safe working load
Above 25 .. (1.22 x safe working load)+20
(b) In the case of a single sheave block, the safe working load shall be the
maximum load which can safely be lifted by the block when suspended by its
head fitting and the load is attached to a rope which passes around the sheave
of the block and a test load not less than four times the proposed safe working
load shall be applied to the head of the block.
(c) In the case of multi sheave block, the test load shall not be less than the load as
specified in the following table:—
TABLE
Safe working load Test load
(in tonnes) (in tonnes)
Upto 25 .. 2 x safe working load
25 to 160 .. (0.9933 x safe working load)+27
above 160 .. 1.1 x safe working load.
(d) In the case of hand-operated pulley blocks used with pitched chains and rings.
hooks, shackles or swivel, permanently attached thereto, a test load not less
than 50 per cent in excess of the safe working load shall be applied.
(e) In the case of a pulley block fitted with a bucket, the bucket shall be tested and
the load applied to the bucket when testing that block will be accepted as test
load of the bucket.
(f) In the case of sling having two legs, the safe working load shall be calculated
when the angle between the legs is 90 degree. In case of multi-legged slings
the safe working load shall be calculated as per national standards.
(g) Every lifting beam, lifting frame, container spreader bucket, tub. or other
similar devices shall be subjected to a test load which shall not be less than the
load as specified in the following table:—
-102-
TABLE
Proposed safe working load Test load
(in tonnes) (in tonnes)
Upto 10 .. 2 x safe working load
10 to 160 .. (1.04 x safe working load)+9.6
Above 160 .. 1.1 x safe working load.
(h) Wire ropes.—In the case of wire ropes a sample shall be tested to destruction.
The test procedure shall be in accordance with recognised national standards.
The safe working load of the rope is to be determined by dividing the load at
which the sample broke by a co-efficient of utilisation, determined as specified
in the following table:--
TABLE
Item . Co-efficient of Utilisation
(1) (2)
(a) Wire rope forming part of sling safe
working load of the sling; safe working 5
load upto and equal to 10 tonnes
Safe working load above 10 tonnes
and upto and equal to 160 tonnes. 10
(8.85 x safe working load +1910
Safe working load above 160 3
(b) Wire rope as integral part of a lifting
appliance safe working load of the
lifting appliance: Safety working load
upto and equal to 160 tonnes
10
(8.85 x safe working load +1910
Safe working load above 160 tonnes. 3
(i) Before any test is carried out, a visual inspection of the lifting appliance, or
lifting gear involved shall be conducted and any visible defective gear shall be
replaced or renewed.
(j) After being tested, all the lifting gears shall be examined to see whether any
parts have been injured or permanently deformed by the test.
-103-
Procedure for testing:
(3) Derricks.- (a) A Derrick shall be tested with its boom at the minimum angle to the
horizontal for which the derrick is designed (generally 15 degrees) or at such greated angle as
may be agreed. The angle at which the test has been carried out shall be mentioned in the test
certificate. The test load shall be applied by hoisting movable weights. During the test, the
boom shall be swung with the test load, as far as practicable, in both directions.
(b) A derrick boom, designed to be raised with power, with the load suspended, shall,
in addition to the test at (a), be raised (with the load suspended) to its maximum
working angle to the horizontal and the two outermost positions.
(c) While test loading of a heavy lift derrick the competent person responsible for
tests using movable weights shall ascertain from the owner of the vessel or
floating platform that the stability of the vessel or platform is adequate for the test.
(4) The derricks tested under clause (3) shall not be used in union purchase rigs unless,-
(a) the derricks rigged in union purchase are tested with the test load appropriate to the safe
working load in union purchase (at the designed headroom and with the derrick booms their
approved working positions):
(b) the safe working load of that derrick in union purchase rig has also been specified
by a competent person in a report in Form-V:
(c) any limitations or conditions specified in the said report are complied with; and
(d) the two hoist ropes are coupled together by a suitable swivel assembly.
Explanation,--The safe working loads of derricks (for each method of rig including union
purchase) shall be shown or the Certificate of test and marked on the derrick booms.
(5) Lifting appliances.- (a) The test loads shall be lifted and swung . as far as possible, in
both directions. If the jib or boom of the crane has a variable radius, it shall be tested with test
loads at the maximum and minimum radii. In case of hydraulic cranes when owing to the
limitation of pressure, it is impossible to lift a test load in accordance with table under item
(1). it will be sufficient to lift the greatest possible load which shall be more than safe
working load.
(b) The test shall be performed at maximum, minimum and intermediate radius points
as well as such points in the arc of rotation, as the competent person may decide. The test
shall consist of hoisting, lowering, breaking and swinging and swinging through all positions
and operations normally performed. An additional test shall be made by operating the
machinery at maximum working speed with the safe working load suspended.
(6) Use of spring or hydraulic balances, etc. for test loading.- All tests shall normally be
carried on with the help of dead weights. In case of periodical test. replacements or renewals,
test load may be applied by means of suitable springs or hydraulic balances. In such case. test
load shall be applied with the boom, as far out as practicable, in both directions. The test shall
not be taken as satisfactory unless the balance has been certified for accuracy by the
-104-
competent authority within 20 percent and the pointer of the machine has remained constant
at the test load for a period of at least five minutes.
(7) Testing machines and dead weights.- (a) A suitable testing machine shall be used for
testing of chains, wire ropes and other lifting gears:
(b) Testing machined and balances to be used in test loading, testing and checking
shall not be used unless they have been certified for accuracy at least once in the
preceding twelve months by the competent authority; and
(c) Movable weights used for the test loading of the lifting appliances having a safe
working load not exceeding twenty tonnes shall be checked for accuracy by means
of suitable weighing machine of certified accuracy.
(8) Through examination after testing or test loading.- After being test loaded, every
lifting appliance and associated gear shall be thoroughly examined to see that no part has
been damaged or permanently deformed during the test. For this purpose, the lifting
appliance or gear shall be dismantled to the extent considered necessary by the competent
person.
SCHEDULE-II.
Notifiable Occupational Diseases in Building and other Construction work.
[(See rule 230(a)]
1. Occupational dermatitis.
2. Occupational Cancer.
3. Asbestos.
4. Silicosis.
5. Lead poisoning including poisoning by any preparation or compound
of lead or their sequelae.
6. Benzene poisoning, including poisoning by any of its homologues,
their nitro or amino derivatives or its sequelae.
7. Occupational asthama.
8. Pesticide poisoning.
9. Carbon monoxide poisoning.
10. Toxic Jaundice.
11. Toxic anaemia.
12. Compressed air illness (Caissons disease).
12. Noise induced hearing loss.
13. Isocyanates poisoning.
14. Toxic nephritis.
-105-
SCHEDULE-IlI
Contents of a First-aid Box
[See rule 231 (b)]
(k) A sufficient number of eye wash bottled filled with distilled water suitable
liquid clearly indicated by a distinctive sign which shall be visible at all times.
(ii) 4 percent xylocaine eye drops, and boric acid eye drops and soda by
carbonate eye drops.
(iii) Twenty four small sterilized dressings.
(iv) Twelve medium size sterilised dressings.
(v) Twelve large size sterilised dressings.
(vi) Twelve large size sterilised burn dressings.
(vii) Twelve (fifteen) and packets of sterlised cotton wool.
(viii) One (Two hundred millilitre) bottle of certimide solution (1 per cent) or
suitable antiseptic solution.
(ix) One (two hundred millilitre) bottle of mercurochrome (2 percent) solution
in water.
(x) One (one hundred twenty millilitre) bottle of sal-volatile having the doses
and mode of administration indicated on the label.
(xi) One pair of scissors.
(xii) One roll of adhesive plaster (six centimeter x one metre)
(xiii) Two rolls of adhesive plaster (two centimeters x one metre)
(xiv) Twelve pieces of sterilised eye pads in separate sealed packets.
(xv) A bottle containing hundred tablets (each of three hundred twenty five
milligram) of aspirin or any other analgesic.
(xvi) Twelve roller bandages ten centimeters wide.
(xvii) Twelve roller bandages five centimeters wide.
(xviii) One tourniquet.
(xix) A supply of suitable splints.
(xx) Three packets of safety pins.
(xxi) Kidney tray.
(xxii) A snake bite lancet.
(xxiii) One (thirty milliltire) bottle containing potassium permanganate crystals.
(xxiv) One copy of first-aid leaflet issued by the Directorate General.
(xxv) Six triangular bandages.
-106-
(xxvi) Two pairs of suitable, sterilised, latex hand gloves.
SCHEDUI.E - IV
(Articles for ambulance room)
{See rule 226 (c)}
(i) A glazed sink-with hot and cold water always available.
(ii) A table with a smooth top at least 180/ centimeters x 105 centimeters.
(iii) Means for sterilising instruments.
(iv) A couch.
(v) Two stretchers.
(vi) Two buckets or containers with close fitting lids.
(vii) Two rubber hot water bags.
(viii) A kettle and spirit stove or other suitable means of boiling water.
(ix) Twelve plain wooden splints 900 centimeters x 100 centimeters x 6 centimeters.
(x) Twelve plain wooden splints 350 centimeters x 75 centimeters x 6 centimeters.
(xi) Six plain wooden splints 250 centimeters x 50 centimeters 12 centimeters.
(xii) Six woolen blankets.
(xiii) Three pairs artery forceps.
(xiv) One bottle of spiritus annemiae aremations (120 millilitre).
(xv) Smelling salt (60 grams).
(xvi) Two medium size sponges.
(xvii) Six hand towels.
(xviii) Four kidney trays.
(xix) Four cakes of toilet, preferably antiseptic soap.
(xx) Two glass tumblers and two wine glasses.
(xxi) Two clinical thermometres.
(xxii) Two tea spoons.
(xxiii) Two graduated (120 millilitre) measuring glasses.
(xxiv) Two minimum measuring glasses.
(xxv) One wash bottle (1000 cubic centimetre) for washing eyes.
(xxvi) One bottle (one litre) carbolic lotion 1 in 20.
(xxvii) Three chairs.
(xxviii)One screen.
(xxix) One electric hand torch.
-107-
(xxx) Four first-aid boxes or cupboards stocked to the standards prescribed in the Schedule
III.
(xxxi) An adequate supply of tetanus toxide.
(xxxii) Injections-morphia. pethidine. atrophine. adrenaline, coramine, novacaine (6 each).
(xxxiii)Cramine liquid (60 millilitre).
(xxxiv) Tablets - antihistaminic antispasmodic (25 each)
(xxxv) Syringes with needles-2 cubic centimetres, 5 cubic centimetres, 10 cubic centimetres
and 500 cubic centimetres.
(xxxvi) Three surgical scissors.
(xxxvii) Two needle holders, big and small.
(xxxviii) Suturing needles and materials.
(xxxxi) Three dissecting forceps.
(xl) Three dressing forceps.
(xli) Three scalpels.
(xlii) One stethoscope and a B.P. apparatus.
(xliii) Rubber bandage - pressure bandage.
(xliv) Oxygen cylinder with necessary attachments.
(xlv) Atropine eye ointments.
(xlvi) I.V. Fluids and sets 10 numbers.
(xlvii) Suitable, foot operated covered, refuse containers.
(xxxxviii )Adequate number of sterilised. paired, latex hand gloves.
SCHEDULE - V.
Contents of Ambulance Van or Carriage.
[See rule 227]
The Ambulance Van shall have equipment prescribed as under,—
(a) General.- A portable stretcher with folding and adjusting devices with the head of the
stretcher capable of being tilted upward. Fixed suction unit with equipment. Fixed
oxygen supply with equipment. Pillow with case, sheets, blankets, towels, emergency
bag, bed pan, urinal glass.
(b) Safety Equipment.- Flaros with life of three thousand minutes, floor lights, flash lights,
fire extinguishers (dry powder type), insulated guntlets
-108-
(c) Emergency Care Equipment.- (i) Resuscitation: Portable suction unit. portable oxygen
unit. bagvalve mask. hand operated artificial ventilation unit, airways, mouthgag
tracheostomy adapters, short spine board. l.V. Fluids with administration unit. B.P.
manometer, cuff stethoscope.
(ii) Immobolisation- Long and short padded boards, wire ladder splints,
triangular bandage - long and short spine boards.
(iii) Dressing.- Gauze pads- 100 millimeter x 100 millimeter universal dressing
250 x 1000 millimeters roll of aluminium foils- soft roller bandages 150
millimeter x 5 millimeter yards adhesive tape in 75 millimeter roll of
safety pins, bandage sheets, burn sheets.
(iv) Poisoning.- Syrup of Ipecac, activated charcoal prepacketed does, snake
bite kit. drinking water.
(v) Emergency Medicine.- as per requirement (under the advice of
construction Medical Officer).
SCHEDULE-VI .
Permissible Exposure in cases of Continuous Noise.
(See rule 34)
Total time of exposure (continuous /or number of short -term
exposures) per day (in hours)
Sound pressure
level.(in dBA)
(1) (2)
8 90
6 92
4 95
3 97
2 100
1 1/2 102
1 105
3/4 107
1/2 110
1/4 115
Explanations- (1) No exposure in excess of 115 dBA is to be permitted.
(2) For any period of exposure falling in between any figure and the next
higher or lower figure as indicated in column (1), the permissible sound
pressure level is to be determined by extrapolation on a proportionate basis.
-109-
SCHEDULE-VII.
Periodicity of Medical examination of building workers.
{See rule 81 (iv) and 223 (a) (iii)}
1. The employer shall arrange a medical examination of all the building workers employed
as drivers, operators of lifting appliances and transport equipment before employing, after
illness or injury, if it appears that the illness or injury might have affected his fitness and
thereafter, once in every two, years upto the age of forty and once in a year, thereafter.
2. Complete and confidential records of medical examination shall be maintained by the
employer or the physician authorised by the employer.
3. The medical examination shall include,--
(a) full medical and occupational history;
(b) clinical examination with particular reference to,—
(i) General Physique.
(ii) Vision.- Total visual performance and standard orthorator like Titmusvision
Tester should be estimated and suitability for placement ascertained in
accordance with the prescribed job standards.
(iii) Hearing.- persons with normal hearing must be able to hear a forced whisper at
twenty four feet. Person using hearing aids must be able to hear a warning shout
under noisy working conditions.
(iv) Breathing- Peak flow rate using standard peak flow meter and the average
peak flow rate determined out of these readings of the test performed. The
results recorded at pro-placement medical examination could be used as
standard for the same individual at the same altitude for reference during
subsequent examination.
(v) Upper limbs.- Adequate arm function and grip (both arms).
(vi) Lower Limbs.- Adequate leg and foot function.
(vii) Spine.- Adequately flexible for the job concerned.
(viii) General.- Mental alertness and stability with good eye, hand and foot
coordination.
(c) Any other tests which the examining doctor considers necessary.
-110-
SCHEDULE-VIII
Number of safety officers, qualification, duties, etc.
[(See Rule 209 (1) and 209 (2)]
Appointment of Safety Officers.
Number of Safety Officers:- Within six months of coming into operation of these rules,
every establishment employing more than five hundred building workers and every other
employer of building worker shall appoint safety officers, as laid down in the scale given
below:-
(1) Upto 1000 building workers - one safety officer.
(2) Upto 2000 building workers - two safety officers.
(3) Upto 5000 building workers- three safety officers.
(4) Upto 10,000 building workers-four safety officers.
For every additional 5000 building workers or part thereof- one safety officer.
Any appointment, when made shall be notified to the lnspector having Jurisdiction in
the area, giving full details of the qualifications, terms and conditions of service of such
safety officer.
Qualification- (a) A person shall not be eligible for appointment as a safety officer unless
he,—
(i) possesses a recognised degree in any branch of engineering or technology or
architecture and had a practical experience of working in a building or other
construction work in a supervisory capacity for-a period of not less than two
years or possesses a recognised diploma in any branch of engineering or
technology and has had practical experience of building or other construction
work in a supervisory capacity for a period of not less than five years;
(ii) possesses a recognised degree or diploma in industrial safety with at least one
paper in construction safety (as an elective subject); and
(iii) has adequate know ledge of Tamil.
(b) Notwithstanding the provision contained in clause (a), any person who,--
(i) possesses a recognised degree or diploma in engineering or technology or
architecture and has had experience of not less than five years in the field,
dealing with the administration of Factories Act, 1948 or the Dock Workers
(Safety, Health and Welfare) Act, 1986 or the Building and Other
Construction Workers (Regulation of Employment and Conditions of Service)
Act, 1996; or
-111-
(ii) possesses a recognised degree or diploma in engineering or technology and
has had experience of not less than five years or has undergone training in
education, consultancy or research in the field of accident prevention in
industry, port or in any institution or an establishment dealing with building or
other construction work;
shall also be eligible for appointment as a safety officer.
Provided that, in case of person who has been working as safety officer in
industry or port. institution or an establishment dealing with building or other
construction work for a period of not less than three years on the date of
commencement of these rules. the Chief Inspector of Building and other
Construction Work may, subject to such conditions that he may specify, relax all
or any of the above said qualification.
Conditions of Service,-- (a) where the number of safety officers appointed
exceeds one, one of them shall be designated as Chief Safety Officer and shall
have the status higher than the others. The Chief Safety Officer shall be in over
all charge of the safety functions as envisaged in sub-clause (iv) and also other
safety officers working under -his control.
(b) the Chief Safety Officer or the Safety Officer, where only one safety
officer is appointed. shall be given the status of a Senior Executive and he
shall work directly under the control of his Chief Executive. All other
safety officers shall be given appropriate status to enable them to dispatch
their functions effectively.
(c) the scale of pay and allowances to be granted to the safety officers
including the Chief Safety Officer and the other conditions of their
service shall be the same as those of the officers of corresponding status
of the establishment in which they are employed.
Duties of Safety Officer.- (a) The duties of a safety officer shall be to advise and
assist the employer in the fulfillment of his obligations, statutory or otherwise
concerning preventive of personal injuries and maintaining a safe working
environment. The duties shall include the following namely;-
(i) to advise the building workers in planning and organising measures
necessary for effective control of personal injuries:
(ii) to advise on safety aspects in a building or other construction work and
to carryout detailed safety studies of selected activities;
(iii) to check and evaluate the effectiveness of action taken or proposd to be
taken to prevent personal injuries;
(iv) to advise purchasing and ensuring quality of personal protective
equipment confirming to national standards;
(v) to carryout safety inspections of building or other construction work in
order to observe the physical conditions of work and the work
-112-
practices and procedures followed by building workers and to render advice
on measures to be adopted for removing unsafe physical conditions and
preventing unsafe actions by building workers;
(vi) to investigate all fatal and other selected accidents;
(vii) to investigate all cases of occupational diseases contracted and
reportable dangerous occurrences;
(viii) to advise on the maintenance of such records as are necessary with
regard to accidents, dangerous occurrences and occupational diseases;
(ix) to promote the working of safety committees and to act as an advisor
to such committees.
(x) to organise, in association with concerned departments, campaigns,
competitions, contests and other activities which will develop and
maintain the interest of building workers in establishing and
maintaining safe conditions of work and procedures;
(xi) to design and conduct, either independently or in collaboration with
other agencies suitable training and educational programmes for
prevention of accidents to building workers;
(xii) to frame safe rules and safe working practices in consultation with
senior officials of the establishment; and
(xiii) supervise and guide safety precautions to be taken in building and
other construction work of the establishment.
Facilities to be provided to safety officers.- The employer shall provide each safety
officer with such facilities, equipment and information that are necessary to enable him to
despatch his duties effectively.
Prohibition of performance of other duties.- No safety officer shall be required or
permitted to do any work which is unconnected to, inconsistent with or detrimental to the
performance of the duties prescribed in this Schedule.
Exemptions.- The Chief Inspector of Building and other Construction Work may,
in writing, exempt any employer or group of employees from any or all of the provisions of
these rules subject to compliance with such alternative arrangements as may be approved and
notified by him in the order of such exemption.
-113-
SCHEDULE -IX
(See rule-225)
Hazardous process.
(1) Roof work.
(2) Steel erection.
(3) Work under and over water.
(4) Demolition.
(5) Work in confined spaces.
SCHEDULE-X.
[See rule 225 (b)]
Services and facilities to be provided in occupational health centres.- (1) One full
time construction medical officer for building or other construction work, employing workers
upto one thousand and one additional construction medical officer for every additional one
thousand workers or part thereof.
(2) The staff, including one nurse, one dresser-cum-compounder, one sweeper-cum-
ward boy with each construction medical officer for full work hours.
(3) The occupational health centre with a floor area of minimum fifteen square metre
constituting two rooms with smooth walls and impern service, adequately
illuminated and ventilated.
(4) Adequate equipment for day to day treatment.
(5) Necessary equipment to manage any medical emergency.
SCHEDULE-XI
[See rule 119 (2) and 225 (c)]
Qualification of construction medical officer - (1) MBBS degree from a medical
institute recognised by the Medical Council of India; and
(2) Diploma in industrial health or equivalent post graduate certificate of training in
industrial health or health.
(3) A medical officer having working experience in organisation / establishments
involved in policy, execution and advice and safety and health of workers
employed in mines, ports and docks. factories and building and other construction
work, for a period of not less than three years may, subject to the satisfaction of the
Chief Inspector of Building and other Construction Work not be required to
possessing the training referred to in item (2) above.
-114-
(4) The syllabi of the courses leading to the above certificates and the organisation
conducting such courses shall be approved by the Government who may also from
time to time prepare a panel of such organisations.
(5) Complete particulars including name, qualification and experience of the
construction medical officer will be intimated to the inspector having jurisdiction.
SCHEDULE-XII.
[See rule 152(a)]
PERMISSIBLE LEVELS OF CERTAIN CHEMICAL SUBSTANCES IN THE WORK
ENVIRONMENT
Sl.
No
Substance
Permissible limit of exposure
Time-weighted
average concentration
(TWA)
(8 hours)
Short-term
exposure limit
(STEL)
(15 minutes)*
ppm Mg/m³** ppm Mg/m³**
1 2 3 4 5 6
01 Acetaldehyde 100 180 150 270
02 Acetic acid 10 25 15 37
03 Acetone 750 1780 1000 2375
04 Aerolein 0.1 0.25 0.3 0.8
05 Acrylonitrile-Skin (S.C.) 2 4.5 - -
06 Aldrin-Skin - 0.25 - -
07 Allyl chloride 1 3 2 6
08 Ammonia 25 18 35 27
09 Aniline-Skin 2 10 - -
10 Anisidine (0-,p-isomers)- Skin 0.1 0.5 - -
11 Arsenic & soluble compounds (as As) - -.2 - -
12 Benzene (S.C.) 10 30 - -
13 Beryllium Compound (As be) (S.C.) - 0.002 - -
14 Boron trifluoride-C 1 3 - -
15 Bromine 0.1 0.7 0.3 2
16 Butane 800 1900 - -
17 2-Butanone
MBK)
(Methyl ethyl Ketone- 200 590 300 885
115
18 n-Butyl acetate 150 710 200 950
19 n-Butyl alcohol-Skin-0 50 150 - -
20 Sec/tert, Butyl acetate 200 950 - -
21 Butyl mercaptan 0.5 1.5 - -
22 Cadmium dust and salts (as Cd) - 0.05 - -
23 Calcium oxide - 2 - -
24 Carbary (sevin) - 5 - -
25 Carbofuran (Furadan) - 0.1 - -
26 Carbon disulphide-Skin 10 30 - -
27 Carbon monoxide 50 55 400 440
28 Carbon tetrachloride-- Skin (S.C.) 5 30 - -
29 Chlordane-Skin - 0.5 - -
30 Chlorine 1 3 3 9
31 Chlorobenzene (Monochlororbenzene) 75 350 - -
32 Chloroform (S.C.) 10 50 - -
33 Bis (Chloromethyl) ether (H.C.) 0.001 0.005 - -
34 Chromic acide chromates (as Cr,)
(Water soluble)
- 0.05 - -
35 Chromous salts (as Cr.) - 0.5 - -
36 Copper-fume - 0.2 - -
37 Cotton dust, raw - 0.2* - -
38 Cresol, all isomers-Skin 5 22 - -
39 Cyanides (as CN)-Skin - 1 - -
40 Cyanogen 10 20 - -
* line free dust as measured by the vertical eluviator cotton-dust sampler.
(1) (2) (3) (4) (5) (6)
41. Dichlorodiphenyl trichloroethane - 1 - -
42. Demeton-Skin 0.01 0.01 - -
43. Diazinion-Skin - 0.01 - -
44. Dibutyl Phthalate - 5 - -
45. Dicholorvos (DDVP)-Skin 0.01 1 - -
46. Dieldrin-Skin - 0.25 - -
47. Dintrobenzene (all isomers)-Skin 0.15 1 - -
48. Dinitroteoluene-Skin - 1.5 - -
49. Dipheny (Diphenyl) 0.2 1.5 - -
50. Endosulfan (Thiodan)-Skin - 0.1 - -
51. Endrin-Skin - 0.1 - -
-116-
52. Ethyl acetate 400 1400 - -
53. Ethyl alcohol 1000 1900 - -
54. Ethylamine 10 18 - -
55. Fluordies (as F) - 2.5 - -
56. Flucrine 1 2 2 4
57. Formaldehyde (S.C.) 1.0 1.5 2 3
58. Formic acid 5 9 - -
59. Gasoline 300 900 500 1500
60. Hydrazine-Skin (S.C.) 0.1 0.1 - -
61. Hydrogen Chloride-C 5 7 - -
62. Hydrogen Cyanide-Skin-C 10 10 - -
63. Hydrogen fluorine (as F).C 3 2.5 - -
64. Hydrogen peroxide 1 1.5 - -
65. Hydrogen sulphide 10 14 15 21
66. Iodine-C 0.1 1 - -
67. Iron Oxide Fume (Feo) (as Fe) - 5 - -
68. Isoamyl acetate 100 525 - -
69. Isoamyl alcohol 100 360 125 450
70. Isobuty alcohol 50 150 - -
71. Lead, inorg, dusts and fumes (as Pb) - 0.15 - -
72. Lindane-Skin - 0.5 - -
73. Malathion-Skin - 10 - -
74. Manganese dust and compounds
(as Mn)-C
-
5
-
-
75. Manganese fume (as Mn) - 1 - -
76. Mercury (as Hg)-Skin
(i) Alkyl compounds - 0.01 - 0.30
(ii) All forms except alkyl vapour - 0.05 - -
(iii) Atyl and inorganic compound - 0.1 - -
77. Methyl alchol (Methanol)-Skin 200 0.260 250 310
78. Methyl cellosolve
(2-Methoxy-ethanol)-Skin
5
16
-
-
79. Methyl isobutylketone 50 305 75 300
80. Methyl isocyanate-Skin 0.02 0.05 - -
81. Napthalene 10 50 15 75
82. Nickel carbonyl (as Ni) 0.05 0.35 - -
83. Nitric acid 2 5 4 10
84. Nitric Oxide 25 30 - -
85. Nitrobenzene-Skin 1 5 - -
86. Nitrogen dioxide 3 6 5 10
87. Oil mist, mineral - 5 - 10
88. Ozone 0.1 0.2 0.3 0.6
89. Parathion-Skin - 0.1 - -
90. Phenol-Skin 5 19 - -
91. Phorate (Thimet)-Skin - 0.05 - 0.2
92. Phosgene (Carbonyl Cholride) 0.1 0.4 - -
93. Phosphine 0.3 0.4 1 1
94. Phosphoric acid - 1 - 3
-117-
95. Phosphorus (Yellow) - 0.1 - -
96. Phosphorus Pentachloride 0.1 1 - -
97. Phosphorus trichloride 0.2 1.5 0.5 3
98. Pieries acid-Skin - 0.1 - 0.3
99. Pyridine 5 15 - -
100. Silane (Silicon tetrahy dride) 5 7 - -
101. Sodium hydroxide-C - 2 - -
102. Styrene,monomer (Phenylethylene) 50 215 100 425
103. Sulphur dioxide 2 5 5 10
104. Sulphur hexafluroride 1000 6000 - -
105. Sulphuric acid - 1 - -
106. Tetraethyl lead (as Pb)-Skin - 0.1 - -
107. Tolune 100 375 150 560
108. O-Toluidine-Skin (S.C.) 2 9 - -
109. Tributyl phosphate 0.2 2.5 - -
110. Trichloroethylene 50 270 200 1080
111. Uranium, natural (as U) - 0.2 - 0.6
112. Vinyl chloride (H.C.) 5 10 - -
113. Welding fumes - 5 - -
114. Xylene (o-m-, p-isomers) 100 435 150 655
115. Zinc Oxide
(i) Fume - 5.0 - 10
(ii) Dust (Total Dust) - 10.0 - -
116. Zirconium compounds (as Zr.) - 5 - 10
ppm : Parts of vapour or gas per million parts of contaminated air by volume
at 25ºC and 760 mm of Hg.
mg/m³ : Milligram of substance per cubic metre of air.
* : Not more than 4 times a day with atleast 60 min. interval
between successive exposures.
**Mg/M³ : Molecular weight x ppm
24.45
'c' : denotes Ceiling Limit.
'Skin' : Denotes potential contribution to the overall exposure by the cutaneous
route including mucous membranes and eye.
'S.C.' : Denotes Suspected Human Careinogen.
'H.C.' : Denotes Confirmed Human Careinogen.
Substance Permissible time-weighted average
Concentration (TWA) (8.Hrs.)
Silica, S1O2
(a) Crystalline
i) Quartz
-118-
(1) In terms of dust count 10600
----------------------- mppcm
% Quartz + 10
(2) In terms of respirable dust 10
------------------------------- mg/m³
% respirable Quartz + 2
(3) In terms of total dust 30
---------------------- mg/m³
% Quartz + 3
ii) Cristobalite Half the limits given against quartz.
iii) Tridymite Half the limits given against quartz.
iv) Silica, fused Same limits as for quartz.
v) Tripoli Same limits as in formula in item (2)
given against quartz.
b) Amorphous Silicates
Asbestos (H.C.)
10 mg/m³, Total dust.
* 2 fibres/ml, greater than 5µm in length and
less than 3µm in breadth with length to
breadth ratio equal to or greater than 3:1
Portland Cement 10 mg/m³, Total dust containing less than
1% quartz.
Coal Dust 2 mg/m³, respirable dust fraction containing
less than 5% quartz.
----------------------------------------------------------------------------------------------------------------
Mppcm : Million particles per cubic metre of air, based on impinger
samples counted by light-field techniques.
* : As determined by the membrane filter method at 400-450 x magnification
(4 mm objective) phase contrast illumination.
SCHEDULE - XIII
Previous and next
Questions people ask
Is rule 252 of Tamil Nadu Building And Other Construction Workers (Regulation Of Employment And Conditions Of Service) Rules,2006 still in force?
No repeal of Tamil Nadu Building And Other Construction Workers (Regulation Of Employment And Conditions Of Service) Rules,2006 is recorded.