LawGrids logoLAWGRIDS.ORG

Rule 103, THE BUILDING AND OTHER CONSTRUCTION WORKERS' (REGULATION OF EMPLOYMENT AND CONDITIONS OF SERVICE) JHARKHAND RULES, 2006: Mixing and pouring of concrete

THE BUILDING AND OTHER CONSTRUCTION WORKERS' (REGULATION OF EMPLOYMENT AND CONDITIONS OF SERVICE) JHARKHAND RULES, 2006 - Rule 103

Text of rule 103

Mixing and pouring of concrete

103. Mixing and pouring of concrete. - the employer shall ensure at a construction site of a building or other construction work that - (a) the concrete mixture does not contain any material which may unduly affect the setting of such concrete, weaken such concrete or corrode steel used with such concrete ; (b) when dry ingredients of concrete are being mixed in confined spaces such as silos, (i) the dust shall be exhausted at the time of such mixing and (ii) in case the dust cannot be exhausted, as specified in sub-clause (i), the building workers shall wear respirators at the time of such mixing ; (c) when concrete is being tipped from buckets, building workers are kept out of the range of any kickbacks of such buckets ; (d) loads are not dumped or placed on settling concrete.

Previous and next

All provisions of THE BUILDING AND OTHER CONSTRUCTION WORKERS' (REGULATION OF EMPLOYMENT AND CONDITIONS OF SERVICE) JHARKHAND RULES, 2006

Questions people ask

Is rule 103 of THE BUILDING AND OTHER CONSTRUCTION WORKERS' (REGULATION OF EMPLOYMENT AND CONDITIONS OF SERVICE) JHARKHAND RULES, 2006 still in force?

No repeal of the BUILDING AND OTHER CONSTRUCTION WORKERS' (REGULATION OF EMPLOYMENT AND CONDITIONS OF SERVICE) JHARKHAND RULES, 2006 is recorded.