Regulation 6, The Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006: Additional surcharge
The Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006 - Regulation 6
Text of regulation 6
Additional surcharge
6. Additional surcharge.-(1) An open access consumer shall also pay to the
distribution licensee an additional surcharge to meet the fixed cost of such distribution
licensee arising out of his obligation to supply as provided under sub-section (4) of section
42 of the Act.
(2) Additional surcharge will be payable by any consumer including any
consumer who puts up a captive plant for his own use.
(3) The additional surcharge for obligation to supply as per sub-section 4 of
section 42 of the Act shall become applicable only if it is conclusively demonstrated that
the obligation of a licensee, in terms of existing power purchase commitments, has been
and continues to be stranded, or there is an unavoidable obligation and incidence to bear
fixed costs consequent to such a contract. The fixed costs related to network assets would
be recovered through wheeling charges.
(4) Each distribution licensee shall submit to the Commission, details of fixed
costs, which the licensee is incurring towards his obligation to supply.
(5) In determining the additional surcharge, the Commission shall scrutinize the
details of fixed costs submitted by the distribution licensee and invite and consider
objections, if any, from the public and affected parties.
(6) The additional surcharge shall be determined on annual basis and it can be
collected either as onetime payment or on monthly basis.
“4. Reduction and Elimination of cross-subsidy surcharge. - (1) The phasing of the cross subsidy surcharge
shall be within a period of five years, and the cross subsidy surcharge at the end of 5 years shall be at a
normative level of 20% of its opening level in the base year.
(2) The base year for starting the elimination of cross subsidy surcharge shall be the financial year
2006 and the phasing will be in terms of percentage of the cross subsidy surcharge to be made applicable to the
Open Access Customer – starting from 100% in the first year to 20% in the sixth year as detailed in the
Table hereunder:-
Year Phasing Plan
FY06 100%
FY07 84%
FY08 68%
FY09 52%
FY10 36%
FY11 20%
4 Compendium of HPERC Regulations, March 2021
1
[7. XX XX XX XX XX XX XX]
Previous and next
Questions people ask
Is regulation 6 of the Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006 is recorded.