Unscheduled Inter-change (UI) charges
20. Unscheduled Inter-change (UI) charges.-(i) The mismatch betwesn
the scheduled and the actual drawal at drawal point(s) and scheduled and the actilial
injection point(s) shall be met from the grid and shall be governed ur pricihg
mechanism applicable to the Inter-State transactions as per ABT Tariff. · I,
(ii) A separate bill for UI charges shall be issued to the direct customers a,nd in
case of the embedded customers, a composite U! bill for the.State as a whole sliall
be issued the segregation for which shall be done at the State level by SLDC. JI
Previous and next
All provisions of JSERC (open access inter state transmission & distribution) regulation 2005