Regulation 3, The Himachal Pradesh Electricity Regulatory Commission (Security Deposit) Regulations, 2005: Power to require security
The Himachal Pradesh Electricity Regulatory Commission (Security Deposit) Regulations, 2005 - Regulation 3
Text of regulation 3
Power to require security
3. Power to require security.- (1) The distribution licensee shall require every person,
who requires a supply of electricity to his premises in pursuance of section 43 of the Act,
to give security as provided in regulation 4, for the payment of all monies, which may
become due to the licensee -
(a) in respect of the electricity supplied to such person; or/and
(b) where any electric line or electrical plant or electric meter is to be provided for
supplying electricity to such person, in respect of the provision of such line,
plant and/or meter.
1
[Provided that the licensee may not obtain such security in case where the supply
of electricity is required for its own use.]
(2) If such person fails to give such security under sub-regulation (1), the
distribution licensee may refuse to give the supply of electricity or to provide the line or
plant or meter for the period during which the failure continues.
Previous and next
Questions people ask
Is regulation 3 of the Himachal Pradesh Electricity Regulatory Commission (Security Deposit) Regulations, 2005 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Security Deposit) Regulations, 2005 is recorded.