Text of section 92
92. (1) On allotment of land to, and possession thereof by the co-operative housing
society, the committee shall appoint the architect and the contractor with a
provision that construction shall be completed as per time limit fixed for
completion of construction of the housing project of the society in the sanction
letter conveying approval of layout and building plans by the sanctioning authority
under the applicable building bye-laws or within five years from the date of
sanction of layout and building plans by the competent civic authority, whichever
is earlier, with the prior approval of the general body:
Provided that if due to unforeseen circumstances, the aforesaid time limit cannot
be adhered, the committee shall approach the Government for further extension
of time to complete the project with the approval of its general body at least one
hundred and eighty days in advance and failure to adhere to the above time limit
by the committee shall be an offence.
(2) After the appointment of the architect and the contractor the committee shall
finalise the likely cost, the time for the execution of the project, the size, category
and design of the flats with a five years defect liability provision to attend defects
in the construction by the concerned contractor and all incidental matters thereto
and get the approval of the general body.
(3) During the construction period, there shall be, at least, two special general
body meetings every year besides one annual general body meeting to give
progress report to the members.
(4) No escalation in cost of the project, and the time fixed for the execution
thereof shall be extended by the committee without the prior approval of the
general body.
(5) There will not be unilateral change of category or size of flat by the committee
without giving an opportunity to the concerned member of hearing after
communicating to him the grounds for change of category or size and preference
shall be given to the existing members in case of any vacancy falling in the
higher category.
(6) All proposals as above, shall be approved by the general body in a meeting
by a majority of not less then two-thirds the * members present in the meeting.
(7) It shall be the responsibility of the committee to ensure quality and structure
stability of the project and the availability of all facilities including electricity,
water, lifts, sewage, roads, mandatory green and landscape, etc. before
allotment.
(8) The Registrar may issue directions and guidelines from time to time in public
interest for timely execution of the project.