Regulation 5, The Himachal Pradesh Electricity Regulatory Commission (Licensee’s Duty for Supply of Electricity on Request) Regulations, 2004: Force Majeure
The Himachal Pradesh Electricity Regulatory Commission (Licensee’s Duty for Supply of Electricity on Request) Regulations, 2004 - Regulation 5
Text of regulation 5
Force Majeure
5. Force Majeure.- The time frame specified in regulation 3 shall not be operative where
the distribution licensee is prevented from giving supply of electricity on account of
cyclones, floods, storms and other occurrences beyond his control.
Previous and next
Questions people ask
Is regulation 5 of the Himachal Pradesh Electricity Regulatory Commission (Licensee’s Duty for Supply of Electricity on Request) Regulations, 2004 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Licensee’s Duty for Supply of Electricity on Request) Regulations, 2004 is recorded.