Regulation 3, The Himachal Pradesh Electricity Regulatory Commission (Licensee’s Duty for Supply of Electricity on Request) Regulations, 2004: Duty of licensee to supply on request
The Himachal Pradesh Electricity Regulatory Commission (Licensee’s Duty for Supply of Electricity on Request) Regulations, 2004 - Regulation 3
Text of regulation 3
Duty of licensee to supply on request
3. Duty of licensee to supply on request.- (1) On the receipt of an application from the
owner or occupier of the premises, every distribution licensee shall, within the time frame
specified hereunder, issue, by a registered post/speed post, a demand notice to the
applicant, clearly indicating –
(a) all deficiencies to be made good and the codal formalities to be completed by
the applicant;
(b) necessity to furnish the test report from the approved Wiring Contractor;
(c) the exact amount of charges and security to be deposited by the applicant:
Type of service connection
requested
Period from date of receipt of
application within which demand
notice should be issued.
Low Tension (LT) supply (10) days
11KV supply (15) days
22 KV supply (15) days
33KV supply (30) days
Extra High Tension (EHT)
supply
(60) days
(2) Every distribution licensee shall, upon the applicant making good the
deficiencies and completion of codal formalities and payment of charges and security, as
indicated in the demand notice under sub-regulation (1), give supply of electricity to the
premises within the time specified in sub-regulation (3).
(3) The distribution licensee shall give supply of electricity to the premises -
(a) where no extension of distribution mains or commissioning of new
sub-station is required for effecting such supply, within twenty days
reckoned from the completion of the codal formalities and the
payment of charges and security amount stated in the demand notice
under sub-regulation (1);
(b) in cases where such extension of distribution mains or commissioning
of new sub-station is required but there is no requirement of erecting
and commissioning a new 33/11kV sub-station, within the time frame
specified hereunder:
Type of service
connection requested
Period from date of completion of
codal formalities required vide
demand notice, within which supply
of electricity should be provided
Low Tension (LT) supply (40) days
11KV supply (30) days
22 KV supply (30) days
33KV supply (60) days
Extra High Tension
(EHT) supply
(120) days
Compendium of HPERC Regulations, March 2021 3
Provided that the distribution licensee may approach the Commission
for extension of the time specified above, in specific cases where the
magnitude of extension is such that the licensee will require more time, duly
furnishing the details in support of such claim for extension and if satisfied
with the justification given by the distribution licensee, the Commission
may extend the time for commencing the supply;
(c) in the case of application for new connection, where extension of supply
requires erection and commissioning of new 33/11 KV sub-station, the
distribution licensee shall, within 15 days of receipt of application, submit
to the Commission a proposal for erection of 33/11 KV sub-station together
with the time required for commissioning the sub-station. The Commission
shall, after hearing the distribution licensee and the applicant concerned,
decide on the proposal and the time frame for erection of the sub-station.
The distribution licensee shall erect and commission the sub-station and
commence power supply to the applicant within the period approved by the
Commission:
Provided that, where such sub-station is covered in the investment plan
approved by the Commission, the distribution licensee shall complete the
erection of such sub-station within the time period specified in such
investment plan.
(4) The distribution licensee shall not be responsible for the delay, if any, in
extending the supply, if the same is on account of problems relating to right of way,
acquisition of land, or the delay in consumer’s obligation to obtain approval of the Chief
Electrical Inspector for his High Tension or Extra High Tension installation, or for any
other similar reasons beyond the reasonable control of the distribution licensee:
Provided that if any dispute arises whether the delay in extending the supply is
attributable to the reasons beyond the control of the distribution licensee or not, it shall be
decided by the Commission and the decision of the Commission shall be final and
binding.
(5) Subject to the above it shall be the responsibility of the distribution licensee to
have necessary commercial arrangements with the respective transmission licensee(s) to
ensure that the required supply at Extra High Tension (EHT), i.e. above 33 KV, is made
available within the time frame specified under sub-regulation (2).
(6) In cases where the village or hamlet or area is not electrified earlier, the
distribution licensee shall give supply of electricity to premises in such village or hamlet or
area as per the programme of electrification of habitations covered in the investment plan
approved by the Commission, within the time frame specified in such investment plan
approved by the Commission.
Previous and next
Questions people ask
Is regulation 3 of the Himachal Pradesh Electricity Regulatory Commission (Licensee’s Duty for Supply of Electricity on Request) Regulations, 2004 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Licensee’s Duty for Supply of Electricity on Request) Regulations, 2004 is recorded.