Regulation 16, The Himachal Pradesh Electricity Regulatory Commission (General Conditions of Transmission Licence) Regulations, 2004: Connection and use of system
The Himachal Pradesh Electricity Regulatory Commission (General Conditions of Transmission Licence) Regulations, 2004 - Regulation 16
Text of regulation 16
Connection and use of system
16. Connection and use of system.- (1) The transmission licensee shall make such
arrangements for non-discriminatory open access to the use of his transmission system by
the users subject however to the availability of the adequate transmission capacity in
accordance with open access regulations notified by the Commission and further subject to
the users agreeing to pay all applicable charges including the transmission charges and
surcharges wherever applicable.
(2) On application made for grant of a connection by any person intending to use
the transmission system the transmission licensee shall offer to enter into an agreement
with such person for connection to the transmission system or for modification of such an
existing connection and such offer shall make provision for -
(a) carrying out of works necessary to make the required connection, including
the installation of meters;
(b) carrying out of any necessary works to reinforce the transmission licensee’s
transmission system;
(c) the connection charges to be paid as directed by the Commission ; and
(d) the completion date and such other terms as are relevant to the
circumstances.
(3) The transmission licensee shall offer terms for agreements in accordance with sub-
regulations (1) and (2) as soon as practicable to the intended users of the system. The
transmission licensee shall not be obliged to offer to enter into any agreement if-
(a) the adequate transmission capacity is not available in the transmission
system, provided that the existence or absence of such available capacity
shall be subject to determination by the State Transmission Utility and in
case of any dispute pertaining to the same on such determination the same
shall be subject to the decision of the Commission;
(b) it is likely to result in breach of its duties under the Act; or
(c) it is likely to result in breach of any rules or regulations relating to safety or
standards applicable to the transmission business including, the prevailing
rules;
(d) being in breach of any of the grid code;
(e) the person making the application does not undertake to comply with the
grid code from time to time in force to the extent that it is applicable to that
person; or
(f) the person making the application to pay the applicable charges, surcharge,
adjustment for losses of electricity in the transmission systems determined
by the Commission
(4) If, after a period which appears to the Commission to be reasonable for the
purpose, the transmission licensee has failed to enter into an agreement with any intending
user of the transmission system, the Commission may at the request of such intending user
settle such terms in dispute between the transmission licensee and that person and, the
transmission licensee shall forthwith enter into and implement such agreement in
accordance with its terms as settled by the Commission.
18 Compendium of HPERC Regulations, March 2021
(5) The transmission licensee shall prepare and submit to the Commission on an
annual basis, a statement showing in respect of each of the 5 succeeding financial years
forecasts of circuit capacity, power flows and loading on the transmission system under
standard planning criteria, together with,-
(a) such further information as shall be reasonably necessary to enable any
person seeking the use of the system to identify and evaluate the
opportunities available when connecting to and making use of such system;
and
(b) a statement prepared by the transmission licensee indicating its views as to
those parts of its transmission system most suited to new connections and
transport of further quantities of electricity.
(6) At the request of a person or a supplier who wishes to use the transmission
system, the transmission licensee shall prepare an update to the above statement,
incorporating most recent data but specifically including any facility for which any other
person or a supplier has requested use of and connection to the transmission system.
(7) The transmission licensee may make a charge for any statement given or sent to
persons seeking use of system, of an amount reflecting the transmission licensee’s
reasonable costs of providing such a statement.
(8) The transmission licensee is entitled to undertake all activities necessary,
related or incidental to the conduct of the transmission business, which would include
laying and operating appropriate communication network to implement information
technology based solutions like remote metering etc. for the licensed transmission
business.
Previous and next
Questions people ask
Is regulation 16 of the Himachal Pradesh Electricity Regulatory Commission (General Conditions of Transmission Licence) Regulations, 2004 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (General Conditions of Transmission Licence) Regulations, 2004 is recorded.