8. Investments.- (1) The transmission licensee shall duly comply with the regulations,
guidelines, directions and orders the Commission may issue from time to time in regard to
the investments to be made in the transmission business.
(2) The transmission licensee shall make the investment in a prudent manner being
guided by the duty to build, maintain and operate an efficient, co-ordinated and economical
transmission system in the State.
(3) The transmission licensee shall submit to the Commission investment plans as
a part of the business plan under sub regulation (8) of the regulation 7 giving details of
investment schemes to be undertaken during the concerned period for the approval of the
Commission. The transmission licensee shall demonstrate to the satisfaction of the
Commission that -
(a) there is a need for such investments in the transmission system contained in
the investment plan;,
(b) the transmission licensee has examined the economic, technical, system and
environmental aspects of all viable alternatives to the proposal for investing
in or acquiring new transmission system assets to meet such need.
(4) The transmission licensee shall intimate, by the end of the first quarter of each
financial year, -
(a) the annual investment plan with details of investment schemes to be carried
out during the financial year, and
(b) the progress made in implementing the annual investment plan of the
previous financial year with the comparison of actual implementation vis-à-
vis the plan as approved by the Commission for the concerned period.
10 Compendium of HPERC Regulations, March 2021
(5) The transmission licensee shall not undertake schemes involving major
investments, not covered under the investment plan approved by the Commission under
sub regulation (3) without the prior approval of the Commission, and for such approval
the transmission licensee shall demonstrate to the satisfaction of the Commission the
factors mentioned in sub regulation (3).
(6) The transmission licensee shall invite and finalise tenders for procurement of
equipment, material and/or services relating to major investment, in accordance with a
transparent tendering procedure as may be directed by the Commission. The transmission
licensee shall, in consultation with the Commission,-
(i) ensure that the material management policy and practices including
calendar of various actions, approvals, tendering, purchase order, delivery
schedule and payments etc. are streamlined so as to provide necessary
inputs of right quality at the right time to facilitate faithful implementation
and compliance of the approved standards and benchmarks,
(ii) lay down bench-mark prices and conclude rate contracts for decentralised
purchases so as to bring about financial discipline and inventory control for
achieving optimal financial ratios in respect of such decentralised
purchases.
(7) For the purposes of this regulation, the term "major investment" means any
planned investment in or acquisition of transmission facilities, the cost of which, when
aggregated with all other investments or acquisitions (if any) forming part of the same
overall transaction, equals or exceeds an amount contained in the special conditions
applicable to the transmission licensee or otherwise decided by the Commission from time
to time by general or special order.
(8) The transmission licensee shall be entitled to make investment in the transmission
business otherwise than those covered under sub-regulations (3) and (4) but for the
purposes of considering such investment while determining the tariff, the transmission
licensee shall satisfy the Commission that the investment was required for the transmission
business and such investment was made in an efficient, co-ordinated and economical
manner.
(9) The transmission licensee shall submit to the Commission alongwith the
“Expected Revenue Calculations” filed under section 62 of the Act , the highlights of the
annual investment plan consisting of those schemes approved by the Commission, schemes
submitted before the Commission for approval and all schemes not requiring approval of
the Commission planned for the ensuing financial year and shall make investment in the
said financial year in accordance with the said investment plan:
Provided that if any unforeseen contingencies required reallocation of funds within the
schemes listed in the annual investment plan, the transmission licensee may do so to the
extent such reallocation in respect of individual projects does not exceed an amount
decided by Commission in the special conditions applicable to the transmission licensee or
otherwise by a general or special order. The transmission licensee shall give due
intimation of such reallocation to the Commission before making the investment:
Provided also that if on account of unforeseen circumstances the transmission licensee
is required to make investment in a scheme, which does not find a place in the annual
Compendium of HPERC Regulations, March 2021 11
investment plan, the transmission licensee may do so if the same is not a major investment
and subject to the conditions contained in sub regulation (8).
(10) The transmission licensee shall submit to the Commission the relevant load
flow studies and details of investment requirement to achieve the planned reduction both
in technical and non technical losses.
Previous and next
Questions people ask
Is regulation 8 of the Himachal Pradesh Electricity Regulatory Commission (General Conditions of Transmission Licence) Regulations, 2004 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (General Conditions of Transmission Licence) Regulations, 2004 is recorded.