Regulation 19, The Himachal Pradesh Electricity Regulatory Commission (General Conditions of Distribution Licence) Regulations, 2004: Distribution system planning and security standards, distribution system operating standards, overall performance standards
The Himachal Pradesh Electricity Regulatory Commission (General Conditions of Distribution Licence) Regulations, 2004 - Regulation 19
Text of regulation 19
Distribution system planning and security standards, distribution system operating standards, overall performance standards
19. Distribution system planning and security standards, distribution system
operating standards, overall performance standards. - (1) The distribution licensee
shall comply with the existing distribution system planning, security standards and the
existing distribution system operating standards, with such modifications as the
Commission may direct, until the distribution system planning, security standards and
distribution system operating standards proposed by the distribution licensee are approved
by the Commission.
(2) The distribution licensee shall plan, develop and operate its distribution system
in accordance with the distribution system planning and security standards together with
the distribution code as approved by the Commission;
(3) (a) The distribution licensee shall, within such time as the Commission may
direct in the special conditions or otherwise, submit to the Commission the existing
planning and security standards and the operating standards for its distribution system and
the existing planning and security standards and operating standards relating to generation
capacity connected to its distribution system being followed by the distribution licensee.
Such existing standards, with such modification as the Commission may direct, shall
continue to remain in effect until the new standards are approved by the Commission.
(b) The distribution licensee shall, within such time as the Commission may
direct in the special conditions or otherwise, prepare, in consultation with the suppliers,
generating companies, the Central Transmission Utility, the State Transmission Utility, the
Regional Electricity Board and such other persons as the Commission may direct, and
submit to the Commission for approval the distribution licensee's proposal for distribution
planning and security standards and distribution operating standards, and operating
standards in accordance with the general conditions contained in these regulations.
(c) The distribution planning and security standards and distribution operating
standards, and the operating standards submitted by the distribution licensee pursuant to
this regulation, with such modifications as the Commission may require, shall take effect
from such dates as the Commission may direct.
(4) The distribution licensee shall not be in breach of its obligations if the failure to
meet the distribution planning and security standards or the distribution operating
standards is due to force majeure, provided that, the distribution licensee has used its
reasonable efforts, to comply with the distribution planning and security standards or the
distribution operating standards, as the case may be.
(5) The distribution licensee shall, in consultation with suppliers, the generating
companies, the Central Transmission Utility, the State Transmission Utility, the Regional
Electricity Board and such other persons as the Commission may order, review the
standards and their implementation on each occasion a review of the grid code is
undertaken. Following any such review, the distribution licensee shall send to the
Commission -
(a) a report on the outcome of such review; and
(b) any revision which the distribution licensee proposes to make to such
documents from time to time (having regard to the outcome of such review);
and
(c) any written representations or objections (including those not accepted by
the distribution licensee) from suppliers, the generating companies, the
Central Transmission Utility, the State Transmission Utility, the Regional
Compendium of HPERC Regulations, March 2021 21
Electricity Board and such other persons as the Commission may order
arising during the consultation process;
Provided that the Commission may, upon application of the transmission
licensee, relieve the distribution licensee from the obligation to review the
standards and their implementation, to such extent as shall be given in
directions issued to the distribution licensee by the Commission for the
purposes of this condition.
(6) The Commission may, having regard to any written representations and
objections received and following such further consultation as the Commission may
consider appropriate, issue directions requiring the distribution licensee to revise the
standards in such manner as may be given in the directions. The distribution licensee shall
duly carry out the revisions directed by the Commission.
(7) The distribution licensee shall, within 3 months of the end of each financial
year, submit to the Commission a report indicating the performance of the distribution
licensee’s distribution system during the previous financial year. The distribution
licensee’s compliance with the standards of performance may be measured, in part, by the
licensee’s adherence to the distribution code, the supply code, the conditions of supply and
other codes and regulations set forth by the Commission. The distribution licensee shall, if
required by the Commission, publish a summary of the report in a manner approved by the
Commission.
(8) The distribution licensee shall conduct its licensed business in the manner
which it reasonably considers to be the best to achieve the performance standards in
connection with provision of supply services and the promotion of the efficient use of
electricity by the consumers, as may be directed by the Commission by a general or special
order.
(9) The distribution licensee shall provide annually, information to the Commission
as to the means by which it proposes to achieve the performance standards and other
standards applicable to the distribution licensee.
Previous and next
Questions people ask
Is regulation 19 of the Himachal Pradesh Electricity Regulatory Commission (General Conditions of Distribution Licence) Regulations, 2004 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (General Conditions of Distribution Licence) Regulations, 2004 is recorded.