Regulation 10, RIICO Industrial Areas (Prevention of Unauthorised Development and Encroachment) Regulations, 2003: Permission for continuance of unauthorised development or contravention
RIICO Industrial Areas (Prevention of Unauthorised Development and Encroachment) Regulations, 2003 - Regulation 10
Text of regulation 10
Permission for continuance of unauthorised development or contravention
10. Permission for continuance of unauthorised development or contravention. - (1) Where
a person has carried out any unauthorised development on any land as indicated in sub-
section (1) of section 3 of the Act, or continues to use or allows the use of any land or
building in contravention of the provisions of sub-section (2) of section 3 of the Act, be may
apply for permission of continuance of unauthorised development on the land or
continuance of use of the land or the building in contravention of the provisions of the plan,
to the Managing Director or any other officer authorised by him generally or specially in
this behalf, through an application on a plain paper in writing with the copy of the notice
received, stating therein -
(i) the details of the unauthorised development or the contravention of the provisions of
the plan;
(ii) since when the said unauthorised development or the contravention of the provisions
of the plan has been continuing;
(iii) the circumstances under which such unauthorised development or contravention of
the provisions of the plan was made;
(iv) the difficulties which may arise in case of removal of such unauthorised development
of the contravention of the provisions of the plan;
(v) the extent of permission sought for continuance of such unauthorised development or
contravention of the provisions of the plan, with justification;
(vi) the undertaking of compliance, with the terms and conditions including any payment
or reimbursement, specified by the Managing Director or the authorised officer in case
of full or partial permission is allowed; and
(vii) any other relevant fact or statement looking to the specific circumstances of the matter.
(2) On receipt of the application under sub-regulation (1), the Managing Director or the
authorised officer may, after conducting such enquiry as he deems proper, after going into
the facts on record or obtained otherwise and after hearing the person making the
application-
(a) either reject the application for permission in full stating the grounds of rejection in
the order, or
(b) accept the application for permission in full with such terms and conditions as
specified in the order, or
(c) partly accept and partly reject the application for permission, stating the grounds
of part acceptance and of part rejection in the order.
(3) Where the application for permission is rejected in full or in part, the Managing Director
or the authorised officer shall also state in his order as to in which manner and by which
time not exceeding thirty days the person making the application, shall remove the
unauthorised development or contravention of the provisions of the plan.
(4) Where the application for permission is accepted in full or in part, the Managing Director
or the authorised officer shall state in his order as to in which manner and by which time not
exceeding thirty days, the terms and conditions laid down by him for such permission shall
be complied with by the person making the application.
(5) Where in the case of grant of the permission for continuance of unauthorised
development or contravention against the provisions of the plan, in full or in part, the person
making the application fails to comply with the terms and conditions in the manner and the
time, specified in the order of the Managing Director or the authorised officer, the said
permission, in full or part, as the case may be, shall stand withdrawn automatically.
(6) Where the application for permission of continuance of unauthorised development or
contravention of the provisions of the plan is rejected by the Managing Director or where
any permission granted but stands withdrawn under sub-regulation (5), the person making
the application or the person making the default shall be liable to legal action under the
provisions of the Act.
Previous and next
Questions people ask
Is regulation 10 of RIICO Industrial Areas (Prevention of Unauthorised Development and Encroachment) Regulations, 2003 still in force?
No repeal of RIICO Industrial Areas (Prevention of Unauthorised Development and Encroachment) Regulations, 2003 is recorded.