Delhi Electricity Supply Code and Performance Standards (Relaxation) First Order, 2017
Order - THE ELECTRICITY ACT 2003
- Kind: Order
- Under: THE ELECTRICITY ACT 2003
Text of this order
Delhi Electricity Regulatory Commission
Viniyamak Bhavan, C-Block, Shivalik, Malviya Nagar, New Delhi-110017
F.17(174)/Engg./DERC/17-18/5851
Order
(Date of Order: 10.10.2017)
Whereas, provisions of the Regulations 11 (4) (vi) (a) and 16(13) of Delhi Electricity
Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017
stipulate that upto 45kW the electricity connection to the tenants and to the applicants
for temporary connection shall be released through pre-payment meters only.
And whereas, the aforesaid provisions for pre-payment meters have been introduced
for the first time and timely release of electricity connections as mandated under the
Electricity Act, 2003 has to be ensured at the same time.
And whereas, the distribution licensees have sought relaxation in implementation of
aforesaid provisions on the ground that they do not have sufficient number of pre-
payment meters to cater the demand and the process of procurement of pre-payment
meters, though already initiated, may require some more time.
Now, therefore, the Delhi Electricity Regulatory Commission in exercise of its powers
conferred under Regulation 85 of Delhi Electricity Regulatory Commission (Supply Code
and Performance Standards) Regulations, 2017, hereby make this Order to make the
provision in respect of release of connection through pre-payment meters, not
inconsistent with provisions of the Act and the regulation, to relax the performance
standard namely:-
1. Short Title & Commencement :- (1) This order shall be called First Relaxation
Order, 2017.
(2) This order shall come into force on the date of its issue.
2. Supply of electricity through pre-payment meters. The provisions of Delhi
Electricity Regulatory Commission (Supply Code and Performance Standards)
Regulations, 2017 regarding pre-paid meters are relaxed and shall be kept in
abeyance till 31.12.2017. The distribution licensee, till 31.12.2017, may release the
electricity connections through post-payment meters also.
Sd/-
(B. P. Singh)
Member