Delhi Electricity Supply Code and Performance Standards (Relaxation) Second Order, 2019
Order - THE ELECTRICITY ACT 2003
- Kind: Order
- Under: THE ELECTRICITY ACT 2003
Text of this order
Page 1 of 2
Delhi Electricity Regulatory Commission
Viniyamak Bhavan, C-Block, Shivalik, Malviya Nagar, New Delhi-110017
F.17(174)/DERC/Engg./17-18/5856
Order
(Date of Order: 31.5.2019)
Whereas the Delhi Electricity Regulatory Commission (Supply Code and
Performance Standards) Regulations, 2017 (hereinafter referred to as ‘Regulations’)
provide for raising of demand note and payment of charges for release of electricity
connection.
And whereas Regulation 11 (3) (ii) of the Regulations provide that the licensee shall
raise demand note to the applicant, within 2 (two) days of the field inspection
subject to rectification of defects/deficiencies, for applicable charges, giving its
breakup under the heads such as Service Line cum Development (SLD) charges,
Security deposit, security towards pre-payment meter, road restoration charges,
reconnection charges, etc.
And whereas Regulation 11(3)(iii) of the Regulations provide that the applicant shall
make payment within 2 (two) days of the receipt of the demand note.
And whereas Regulation 11(3)(iv) of the Regulations provide for extension of time
for a maximum period of 15 days for making payment of demand note.
And whereas Regulation 11(3)(v) of the Regulations provide for energisation of
connection on receipt of full payment against demand note.
And whereas, the Commission has received the communication from Government of
NCT of Delhi for implementation of reform under Ease of Doing Business for
payment of charges related to connection in first bill.
Now, therefore, the Delhi Electricity Regulatory Commission in exercise of its
powers conferred under Regulation 85 of the Regulations, hereby makes this Order
in respect of the provisions for raising demand note and payment of charges for
release of electricity connection; to relax, namely:-
1. Short Title & Commencement :- (1) This order shall be called Delhi
Electricity Supply Code and Performance Standards (Relaxation) Second Order,
2019.
(2) This order shall come into force on the date of its issue.
2. Payment of Demand Note for release of electricity connection in first
Bill for applicants taking supply at LT level:
(1) The distribution licensee shall raise the demand note to the applicant for
release of electricity connection at LT supply level in the first electricity bill.
Page 2 of 2
(2) The applicant shall be required to pay the demand note for release of
electricity connection within the due date as mentioned in the electricity bill.
(3) In case the electricity bill is not paid by the applicant within the due date, the
licensee shall disconnect the electricity connection as per the provisions of
the Regulation 51 of the Regulations.
Sd/-
(Justice S S Chauhan)
Chairperson