Section 50, Electricity Act 2003: The Electricity Supply Code

Electricity Act 2003 (36 of 2003) - Section 50

Text of section 50

The Electricity Supply Code.

50. The State Commission shall specify an Electricity Supply Code to provide for recovery of electricity charges, intervals for billing of electricity charges disconnection of supply of electricity for non-payment thereof; restoration of supply of electricity; tampering, distress or damage to electrical plant, electric lines or meter, entry of distribution licensee or any person acting on his behalf for disconnecting supply and removing the meter; entry for replacing, altering or maintaining electric lines or electrical plant or meter. 27

Previous and next

All sections of Electricity Act 2003

Questions people ask

Is section 50 of Electricity Act 2003 still in force?

No repeal of Electricity Act 2003 is recorded.