Rule 13, The Goa Command Area Development Rules, 1999: Recovery of dues
The Goa Command Area Development Rules, 1999 - Rule 13
Text of rule 13
Recovery of dues
13. Recovery of dues:— (1) The Command Area Development Board shall, as far as
possible, immediately, but not later than three months after the completion of the
Schemes, intimate the land holder about the amount to be paid by him towards the cost
of works carried out in terms of sub-section (3) of section 19 of the Act.
(2) The rate of interest for the purpose of section 48 of the Act, shall be two percent
more than the rate of interest payable by the Command Area Development Board on
loans raised from credit agencies.
Previous and next
All provisions of The Goa Command Area Development Rules, 1999
Questions people ask
Is rule 13 of the Goa Command Area Development Rules, 1999 still in force?
No repeal of the Goa Command Area Development Rules, 1999 is recorded.