Rule 20, The Tamilnadu Panchayats (Preparation of plans and estimate for works and mode and conditions of contracts) Rules 1998: Opening of sealed Tender cover

The Tamilnadu Panchayats (Preparation of plans and estimate for works and mode and conditions of contracts) Rules 1998 - Rule 20

Text of rule 20

Opening of sealed Tender cover

20. Opening of sealed Tender cover — The Executive Authority or Commissioner or Secretary, as the case may be, or any responsible official authorized by him in this behalf shall, at the time and place specified for the purpose, open the sealed covers containing the Tender in the presence of two officials in that office in addition to the presence of such of the Tenderers or their authorized agents as may be present. Until the sealed covers containing Tenders are so opened, they shall be kept in the personal custody of the Executive Authority or Commissioner or Secretary or of a such official as may be authorised by him in that behalf. On opening the Tenders, the Executive Authority or Commissioner or Secretary, as the case may be, or the Official authorized by him to open the Tenders shall initial all corrections in each Tender which may have been made by the Tenderer and attested by him. If there are corrections in the Tender un-attested by the Tenderer a note of such corrections shall be made on the Tender itself when it is opened. The Executive Authority or Commissioner or Secretary, as the case may be, or the official authorized by him to open the Tenders, shall enter the total number of Tenders received in the Tender Register against each work. 16. GENERAL FUND WORKS 437

Previous and next

All provisions of The Tamilnadu Panchayats (Preparation of plans and estimate for works and mode and conditions of contracts) Rules 1998

Questions people ask

Is rule 20 of the Tamilnadu Panchayats (Preparation of plans and estimate for works and mode and conditions of contracts) Rules 1998 still in force?

No repeal of the Tamilnadu Panchayats (Preparation of plans and estimate for works and mode and conditions of contracts) Rules 1998 is recorded.