Preparation of Contract documents
16. Preparation of Contract documents —(1) Before Tenders are invited for the execution
of a work on Contract, the Executive Authority or Commissioner or Secretary, as the case may be,
shall prepare Contract documents which shall include—
(i) a complete set of drawings showing the general dimensions of the proposed work and
so far as necessary details of the various parts;
(ii) a complete specification of the work to be done and of the materials to be used as
approved by the Director of Rural Development unless reference can be made to some
standard specifications;
(iii) a schedule of the quantities of the various descriptions of the work; and
(iv) a set of conditions of Contract to be complied with by the Tenderer in case his Tender
is accepted.
(2) The draft Tender schedule and Tender conditions shall be got approved from the Technical
Authority concerned competent to accord sanction of estimate before calling for Tenders.
Previous and next
Questions people ask
Is rule 16 of the Tamilnadu Panchayats (Preparation of plans and estimate for works and mode and conditions of contracts) Rules 1998 still in force?
No repeal of the Tamilnadu Panchayats (Preparation of plans and estimate for works and mode and conditions of contracts) Rules 1998 is recorded.