Text of rule 10
Power to entrust the works without Tender
10. Power to entrust the works without Tender — Where Tenders are not called for or are
dispensed with, the Executive Authority or Commissioner or Secretary, as the case may be, shall
except in cases falling under Clauses (a) to (e) of Rule 8 get the work done through a Contractor
selected from the Register of Contractors at rates which shall not ordinarily exceed the sanctioned
estimate rates. Where on the ground of urgency or for other special reason, it is proposed to
allow rates exceeding the sanctioned estimate rates, the previous written approval of the Authority
competent under these Rules to approve the acceptance of Tenders at such rates shall be
obtained:
Provided that any such work may be entrusted to a person in the locality who is not a
registered Contractor, but who is interested in its execution, if in the opinion of the Executive
Authority or Commissioner or Secretary, as the case may be, its execution through such agency is
desirable and if the value or the amount does not exceed rupees two thousand:
Provided further that the selection of Contractors for works, the value or the amount of
which is rupees two thousand or less shall be made by the Block Engineer or Assistant Engineer
(Rural Development):
Provided also that in cases falling under clause (c) of Rule 8, the supplemental maintenance
work shall be entrusted to the Contractor for the original maintenance work at the same rates as
for the original maintenance work.
Previous and next
Questions people ask
Is rule 10 of the Tamilnadu Panchayats (Preparation of plans and estimate for works and mode and conditions of contracts) Rules 1998 still in force?
No repeal of the Tamilnadu Panchayats (Preparation of plans and estimate for works and mode and conditions of contracts) Rules 1998 is recorded.