Rule 4, THE BUILDING & OTHER CONSTRUCTION WORKERS’ WELFARE CESS RULES, 1998: Time and manner of collection
THE BUILDING & OTHER CONSTRUCTION WORKERS’ WELFARE CESS RULES, 1998 - Rule 4
Text of rule 4
Time and manner of collection
4. Time and manner of collection:-(1) The cess levied under Sub-sec. (1) of
Sec. 3 of the Act shall be paid by an employer, within thirty days of completion of
the construction project or within thirty days of the date on which assessment of
cess payable is finalized, whichever is earlier, to the cess collector.
(2) Notwithstanding the provisions of Sub-rule (1), where the duration of the
project or construction work exceeds one year, cess shall be paid within thirty
days of completion of one year from the date of commencement of work and every
1 Notification No G.S.R 149(E), dated 26th March, 1998. Published in Gazette of India,
Extra Part II, Sec. 3(i) dated 26th March 1998.
146 The Building & other Construction Workers‘ Welfare
Cess Rules, 1998
Rule 5
year thereafter at the notified rates on the cost of construction incurred during
the relevant period.
(3) Notwithstanding the provisions of Sub-rule (1) and Sub-rule (2), where
the levy of cess pertains to building and other contraction work of a Government
or of a Public Sector Undertaking, such Government or the Public Sector
Undertaking shall deduct or cause to be deducted the cess payable at the notified
rates from the bills paid for such works.
(4) Notwithstanding the provisions of Sub-rule (1) and Sub-rule (2), where
the approval of a construction work by a local authority is required, every
application for such approval shall be accompanied by a crossed demand draft in
favour of the Board and payable at the station at which the Board is located for
an amount of cess payable at the notified rates from the estimated cost of
construction:
Provided that if the duration of the project is likely to exceed one year, the
demand draft may be for the amount of cess payable on cost of construction
estimated to be incurred during one year from the date of commencement and
further payment of cess due shall be made as per the provisions of Sub-rule (2).
(5) An employer may pay in advance an amount of cess calculated on the
basis of the estimated cost of construction along with the notice of
commencement of work under Sec. 46 of the Main Act by a crossed demand draft
in favour of the Board and payable at the station at which the Board is located:
Provided that if the duration of the project is likely to exceed one year, the
demand draft may be for the amount of cess payable on cost of construction
estimated to be incurred during one year from the date of such commencement
and further payment of cess due shall be made as per the provisions of Sub-rule
(2).
(6) Advance cess paid under Sub-rules (3), (4) and (5), shall be adjusted in
the final assessment made by the Assessing Officer.
Previous and next
All provisions of THE BUILDING & OTHER CONSTRUCTION WORKERS’ WELFARE CESS RULES, 1998
Questions people ask
Is rule 4 of THE BUILDING & OTHER CONSTRUCTION WORKERS’ WELFARE CESS RULES, 1998 still in force?
No repeal of the BUILDING & OTHER CONSTRUCTION WORKERS’ WELFARE CESS RULES, 1998 is recorded.