Rule 3, The Tamil Nadu Lifts and Escalators Rules,1997: Permission to erect a Lift or an Escalator for making additions or alterations to existing Lift or Escalator
The Tamil Nadu Lifts and Escalators Rules,1997 - Rule 3
Text of rule 3
Permission to erect a Lift or an Escalator for making additions or alterations to existing Lift or Escalator
3. Permission to erect a Lift or an Escalator for making additions or alterations to
existing Lift or Escalator.-(1) Every owner of a place intending,-
(a) to erect a Lift or an Escalator in such place; or
(b) to make additions or alterations to existing Lift or Escalator,
shall make an application in Form “A” to the Inspector.
Every such application shall be accompanied by one set of drawings duly
signed by the applicant showing the following particulars, namely:-
(i) Layout of the lift or escalator erection;
(ii) Plan;
(iii) Sectional elevation;
(iv) Arrangement of car and landing doors for lifts;
(v) Lift well enclosures;
(vi) Size and position of the machine relating to the lift well;
(vii) Position of hoisting machine for the lift or escalator;
(viii) Number of floors to be served and total travel by the lift;
2
(ix) Wiring diagram of the complete electrical installations with all
wiring, light points, switch-fuses, control panels and other electrical
apparatus, size of wires, earthing scheme with size of earth leads,
method of construction of earth electrodes, laying of cables for lift or
escalator equipment duly signed by the manufacturer of lift or
escalator or company of Electrical and Mechanical Engineers to
whom the lift or escalator erection work is entrusted and also signed
by the licensed electrical contractor to whom the electrical erection
work is entrusted;
(x) Angle of inclination for an escalator;
(xi) Type of balustrading in an escalator;
(xii) The width between balustrades in an escalator;
(xiii) Details of handrails, step treads, landing, comb plates, trusses or
girders and step wheel tracks in escalator;
(xiv) The rated load in kilograms on escalator;
(xv) The factor of safety based on the static loads in the lift or escalator;
(xvi) The additions or alterations proposed to be made in existing Lift or
Escalator installation shall be shown by distinct colour;
(xvii) Copy of approval obtained from the Urban Local Body concerned for
the Building Plan;
(xviii) A chalan remitted into Government Treasury or by means of
electronic payment through the website https://www.tnei.tn.gov.in for
a fee of, -
(a) Rs.2,500/- (Rupees Two Thousand and Five Hundred only) in
case of lift having 5 landings;
(b) Rs.5,000/- (Rupees Five Thousand only) in case of lift having
more than 5 landings;
(c) Rs.10,000/- (Rupees Ten Thousand only) for each Escalator.
(xix) Structural Stability Certificate obtained from the registered Structural
Engineer for the buildings which are constructed before the formation
of Urban Local Body where additions or alterations are proposed to
be made in the existing lift or escalator installations or where new
Lifts or escalators are proposed to be erected in those buildings.
(2) On receipt of an application under sub-rule(1), the Inspector shall, after
making such inquiries and requiring, the applicant to furnish such
additional information in Form “A” either grant permission in Form ‘’B” or
refuse the permission applied for, within one month from the date of receipt
of the application.”
3
4. Licence for working a Lift or an Escalator,-
(1) Every owner of a place who is permitted to erect a Lift or an Escalator in
such place under rule 3 shall, on completion of such erection of Lift or
Escalator, shall give a notice to the Inspector and shall make an application
to him for a licence. The notice of completion of the erection of Lift or
Escalator and the application for licence shall be in Form “C” along with
the following enclosures,-
(a) a work completion report of the erection of Lift or Escalator in Form “D” as
obtained either from the manufacturer of Lifts or Escalators or a Company
of Electrical and Mechanical Engineers, as the case may be;
(b) a completion report in Form “E” from the licensed electrical contractor;
(c) A chalan remitted into Government Treasury or by means of electronic
payment through the website https://www.tnei.tn.gov.in for a fee of. –
(i) Rs.5,000/-(Rupees Five Thousand only) in case of lift having 5
landings;
(ii) Rs.10,000/-(Rupees Ten Thousand only) in case of lift having more
than 5 landings;
(iii) Rs.10,000/- (Rupees Ten Thousand only) for each Escalator.
(d) Copy of insurance policy taken by the owner of the Lift or Escalator,
covering insurance for the persons using such lift or escalator;
(2) On receipt of an application under sub-rule (1), the Inspector shall
arrange for inspection of the Lift or Escalator within fifteen days and on
getting himself satisfied that all the requirements of the Act and these rules
are complied with, he may grant licence in Form “F” within fifteen days
from the date of receipt of compliance report of rectification of defects, if
any.
Previous and next
All provisions of The Tamil Nadu Lifts and Escalators Rules,1997