Form 4 (Continued), The BayaluSeeme Area Development Board Rules, 1996.: Form No-4 (Continued)
The BayaluSeeme Area Development Board Rules, 1996. - Form 4 (Continued)
Text of form 4 (Continued)
Form No-4 (Continued)
Form No-4 (Continued)
Financial Progress Report of the Project of BayaluSeeme Area Development Board for the Monthof …………….
Sl.
No.
Name of Zone Project site Executive
Agency
Item
number
mentioned
in G.O.No.
……….
Date
…………….
Estimated Cost Date of
commencing
the
execution of
work
Allotment
for the
last year
Expenditure
of the last
year
Allotmen
t for the
current
year
Name of the
Project
Site taluk:
village/city
town
Original
Revised
1 2 3(a) 3(b) 4 5 6(a) 6(b) 7 8 9 10
Expenditure in the current year Allotment from the
date of commencement
Expenditure from the
date of commencement
Scheduled date of
completion
Remarks
Expenditure
incurred till
last month
Expenditure in the
current month
Total Original Revised
11(a) 11(b) 11(c) 12 13 13(a) 13(b) 14
Previous and next
All provisions of The BayaluSeeme Area Development Board Rules, 1996.
Questions people ask
Is form 4 (Continued) of the BayaluSeeme Area Development Board Rules, 1996. still in force?
No repeal of the BayaluSeeme Area Development Board Rules, 1996. is recorded.