Section 214, The Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996
The Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 (27 of 1996) - Section 214
Text of section 214
214. General Provisions:-The employer shall ensure at a construction site
of a building or other construction work that—
(a) all pile-driving equipments are of good design and sound
construction, taking into account the ergonomic principles and
are properly maintained;
(b) a pile driver is firmly supported on a heavy timber sill, concrete
bed or other secured foundation;
(c) in case a pile driver is required to be erected in dangerous
proximity to an electrical conductor all necessary precautions
are taken to ensure safety;
(d) the hoses of steam and air hammer are securely lashed to such
hammer so as to prevent them from whipping in case of
connection or break;
(e) adequate precaution is taken to prevent the pile driver from
overturning;
(f) all necessary precaution is taken to prevent hammer from
missing the pile,;
(g) a responsible person for inspecting pile-driving equipment,
inspects such equipment before taking it into use and takes all
appropriate measures as required for the safety of building
workers before commencing piling work by such equipment.
Previous and next
Questions people ask
Is section 214 of the Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 still in force?
No repeal of the Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 is recorded.