202. Trestle scaffold and cantilever scaffold:-The employer shall ensure
at a construction site of a building or other construction work that—
(a) no trestle scaffold is constructed with more than three tiers or if
its working platform is more than four point five metres above
the ground or floor or other surface upon which such scaffold is
erected, such trestle scaffold is designed by professional engineer
and has the approval of Director General before being taken into
use;
(b) no trestle scaffold is erected on a suspended scaffold;
(c) no cantilever or jib scaffold is used unless it is adequately
supported, fixed and anchored on opposite side of its support
has out-riggers of adequate length and where necessary
sufficiently supported and braced to ensure safety and stability
of such scaffold;
(d) no working platform resting on bearers let into a wall at one end
and without other support is used unless such bearers are of
adequate strength, braced through the wall and securely
fastened on the other side.
Previous and next
Questions people ask
Is section 202 of the Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 still in force?
No repeal of the Building and other Construction Workers‘ (Regulation of Employment and Conditions of Service) Act, 1996 is recorded.